Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,718
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CM1006 # 03 Y:2022 | 03 | 2022 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $454 | $25 | Not Implemented |
CM1006 # 04 Y:2022 | 04 | 2022 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $118 | $0 | Implemented |
CM1006 # 05 Y:2022 | 05 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $156 | $500 | Implemented |
CM1006 # 06 Y:2022 | 06 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $4,160 | $8,000 | Not Implemented |
CM1006 # 07 Y:2022 | 07 | 2022 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $29,546 | $160,998 | Implemented |
MA0845 # 01 Y:2022 | 01 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $108,785 | $906,122 | Not Implemented |
LT8369 # 01 Y:2022 | 01 | 2022 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $12,717 | $30,030 | n/a |
LT8369 # 02 Y:2022 | 02 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $14,592 | $12,831 | n/a |
LT8369 # 03 Y:2022 | 03 | 2022 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $4,568 | $3,852 | n/a |
CW0125 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,655 | $2,019 | n/a |
CW0125 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,007 | $17,900 | n/a |
CW0125 # 03 Y:2022 | 03 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $37,427 | $1,156 | n/a |
CW0125 # 04 Y:2022 | 04 | 2022 | USE SYNTHETIC LUBRICANT | $18,816 | $9,059 | n/a |
CW0125 # 05 Y:2022 | 05 | 2022 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $23,398 | $56,000 | n/a |
CW0125 # 06 Y:2022 | 06 | 2022 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $70,112 | $8,000 | n/a |
CW0125 # 07 Y:2022 | 07 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,449 | $25,995 | n/a |
CW0125 # 08 Y:2022 | 08 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $63,307 | $41,871 | n/a |
UU0208 # 01 Y:2022 | 01 | 2022 | USE POWER DURING OFF-PEAK PERIODS | $9,375 | $9,500 | Not Implemented |
UU0208 # 02 Y:2022 | 02 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $6,476 | $127,045 | Implemented |
UU0208 # 03 Y:2022 | 03 | 2022 | OPTIMIZE PLANT POWER FACTOR | $4,445 | $12,840 | Implemented |
UU0208 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,292 | $7,290 | Implemented |
UU0208 # 05 Y:2022 | 05 | 2022 | INSTALL SKYLIGHTS | $3,058 | $10,560 | Not Implemented |
UU0208 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $230 | $107 | Implemented |
UD1048 # 01 Y:2022 | 01 | 2022 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $15,150 | $1,500 | Not Implemented |
UD1048 # 02 Y:2022 | 02 | 2022 | INSTALL OCCUPANCY SENSORS | $1,915 | $625 | Not Implemented |