Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,942
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0482 # 03 Y:1996 | 03 | 1996 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $40,000 | $10,000 | Not Implemented |
UD0482 # 04 Y:1996 | 04 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,329 | $7,021 | Not Implemented |
UD0482 # 05 Y:1996 | 05 | 1996 | UPGRADE CONTROLS ON COMPRESSORS | $12,397 | $500 | Not Implemented |
UD0482 # 06 Y:1996 | 06 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,360 | $310 | Not Implemented |
UD0481 # 01 Y:1996 | 01 | 1996 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,905 | $6,000 | Not Implemented |
UD0481 # 02 Y:1996 | 02 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $816 | $240 | Implemented |
UD0481 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $409 | $1,565 | Not Implemented |
UD0480 # 01 Y:1996 | 01 | 1996 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,762 | $53,000 | Not Implemented |
UD0480 # 02 Y:1996 | 02 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $43,980 | $20,000 | Not Implemented |
UD0480 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,134 | $10,224 | Not Implemented |
UD0480 # 04 Y:1996 | 04 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,452 | $30,000 | Not Implemented |
UD0480 # 05 Y:1996 | 05 | 1996 | UTILIZE A CENTRAL COOLANT SYSTEM FOR CLEANING AND REUSE OF METAL WORKING FLUID | $5,850 | $0 | Not Implemented |
UD0480 # 06 Y:1996 | 06 | 1996 | METER WASTE WATER | $7,722 | $1,000 | Implemented |
UD0480 # 07 Y:1996 | 07 | 1996 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $6,000 | $6,000 | Not Implemented |
UD0478 # 01 Y:1995 | 01 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,144 | $0 | Not Implemented |
UD0478 # 02 Y:1995 | 02 | 1995 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,021 | $0 | Implemented |
UD0478 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,197 | $4,790 | Implemented |
UD0477 # 01 Y:1995 | 01 | 1995 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $1,927 | $0 | Implemented |
UD0477 # 02 Y:1995 | 02 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,045 | $4,000 | Implemented |
UD0477 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,867 | $5,759 | Implemented |
UD0477 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,444 | $4,300 | Implemented |
UD0477 # 05 Y:1995 | 05 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,196 | $21,000 | Implemented |
UD0477 # 06 Y:1995 | 06 | 1995 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,150 | $250 | Implemented |
UD0477 # 07 Y:1995 | 07 | 1995 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $1,625 | $600 | Not Implemented |
UD0477 # 08 Y:1995 | 08 | 1995 | RECOVER AND REUSE COOLING WATER | $10,234 | $2,500 | Not Implemented |