Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,417
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0413 # 06 Y:1990 | 06 | 1990 | INSULATE BARE EQUIPMENT | $710 | $850 | Not Implemented |
KU0315 # 01 Y:1990 | 01 | 1990 | RECOVER AND REUSE COOLING WATER | $4,123 | $7,000 | Implemented |
KU0315 # 02 Y:1990 | 02 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $862 | $100 | Implemented |
KU0315 # 03 Y:1990 | 03 | 1990 | INSTALL SET-BACK TIMERS | $1,130 | $640 | Implemented |
KU0315 # 04 Y:1990 | 04 | 1990 | OPTIMIZE PLANT POWER FACTOR | $518 | $900 | Not Implemented |
KU0315 # 05 Y:1990 | 05 | 1990 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,282 | $100 | Implemented |
KU0316 # 01 Y:1990 | 01 | 1990 | INSTALL SET-BACK TIMERS | $3,487 | $2,075 | Implemented |
KU0316 # 02 Y:1990 | 02 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $924 | $1,005 | Implemented |
KU0316 # 03 Y:1990 | 03 | 1990 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $7,122 | $15,000 | Implemented |
KU0316 # 04 Y:1990 | 04 | 1990 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $4,990 | $7,200 | Not Implemented |
KU0316 # 05 Y:1990 | 05 | 1990 | OPTIMIZE PLANT POWER FACTOR | $2,160 | $2,250 | Implemented |
KU0316 # 06 Y:1990 | 06 | 1990 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,034 | $1,000 | Implemented |
KU0316 # 07 Y:1990 | 07 | 1990 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $117 | $0 | Not Implemented |
KU0317 # 01 Y:1990 | 01 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $862 | $206 | Implemented |
KU0317 # 02 Y:1990 | 02 | 1990 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,455 | $240 | Implemented |
KU0317 # 03 Y:1990 | 03 | 1990 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,311 | $1,400 | Implemented |
KU0317 # 04 Y:1990 | 04 | 1990 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $453 | $0 | Not Implemented |
KU0317 # 05 Y:1990 | 05 | 1990 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $571 | $950 | Not Implemented |
KU0318 # 01 Y:1990 | 01 | 1990 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $39,803 | $0 | Implemented |
KU0318 # 02 Y:1990 | 02 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,872 | $1,000 | Implemented |
KU0318 # 03 Y:1990 | 03 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $713 | $741 | Implemented |
KU0318 # 04 Y:1990 | 04 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $74 | $90 | Implemented |
KU0318 # 05 Y:1990 | 05 | 1990 | RECOVER AND REUSE COOLING WATER | $65,074 | $27,000 | Not Implemented |
KU0318 # 06 Y:1990 | 06 | 1990 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $61,404 | $0 | Implemented |
KU0318 # 07 Y:1990 | 07 | 1990 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $1,283 | $3,200 | Not Implemented |