Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
143,781
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0653 # 07 Y:2023 | 07 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,961 | $800 | Implemented |
WV0653 # 08 Y:2023 | 08 | 2023 | DEVELOP A REPAIR/REPLACE POLICY | $10,683 | $9,567 | Implemented |
WV0653 # 09 Y:2023 | 09 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,240 | $12,390 | Not Implemented |
WV0653 # 10 Y:2023 | 10 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $5,884 | $14,800 | Implemented |
WV0653 # 11 Y:2023 | 11 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,758 | $2,675 | Implemented |
WV0653 # 12 Y:2023 | 12 | 2023 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $4,538 | $21,440 | Not Implemented |
WV0653 # 13 Y:2023 | 13 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,757 | $1,288 | Implemented |
WV0653 # 14 Y:2023 | 14 | 2023 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $3,320 | $1,500 | Implemented |
WV0653 # 15 Y:2023 | 15 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,200 | $3,036 | Implemented |
WV0653 # 16 Y:2023 | 16 | 2023 | INSULATE BARE EQUIPMENT | $1,621 | $787 | Implemented |
WV0653 # 17 Y:2023 | 17 | 2023 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $1,453 | $7,240 | Not Implemented |
MUCM15 # 01 Y:2023 | 01 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,233 | $216 | Implemented |
MUCM15 # 02 Y:2023 | 02 | 2023 | INSTALL OCCUPANCY SENSORS | $115 | $70 | Implemented |
MUCM15 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,641 | $672 | Implemented |
MUCM15 # 04 Y:2023 | 04 | 2023 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $106 | $50 | Implemented |
MUCM15 # 05 Y:2023 | 05 | 2023 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $2,062 | $10,149 | Not Implemented |
DL0227 # 01 Y:2023 | 01 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,298 | $0 | Implemented |
DL0227 # 02 Y:2023 | 02 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $8,653 | $0 | Implemented |
DL0227 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,027 | $552 | Not Implemented |
DL0227 # 04 Y:2023 | 04 | 2023 | USE OPTIMUM TEMPERATURE | $6,362 | $0 | Implemented |
DL0227 # 05 Y:2023 | 05 | 2023 | USE RADIANT HEATER FOR SPOT HEATING | $3,640 | $10,608 | Not Implemented |
DL0227 # 06 Y:2023 | 06 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $5,836 | $30,292 | Implemented |
CI0022 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $30,795 | $185,422 | n/a |
CI0022 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $18,385 | $60,000 | n/a |
CI0022 # 03 Y:2023 | 03 | 2023 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $17,839 | $9,000 | n/a |