Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,872
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ME0255 # 07 Y:1998 | 07 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,060 | $3,860 | Not Implemented |
ME0255 # 08 Y:1998 | 08 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,945 | $2,860 | Implemented |
ME0255 # 09 Y:1998 | 09 | 1998 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $11,059 | $7,193 | Implemented |
ME0255 # 10 Y:1998 | 10 | 1998 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $9,734 | $15,640 | Not Implemented |
UL0203 # 01 Y:1998 | 01 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,115 | $65 | Implemented |
UL0203 # 02 Y:1998 | 02 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,100 | $20,100 | Not Implemented |
UL0203 # 03 Y:1998 | 03 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $762 | $15 | Implemented |
UL0203 # 04 Y:1998 | 04 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $17,900 | $8,860 | Implemented |
UL0203 # 05 Y:1998 | 05 | 1998 | ELIMINATE/REDUCE AN OPERATION | $109,700 | $16,000 | Not Implemented |
UL0203 # 06 Y:1998 | 06 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $90,000 | $155,600 | Not Implemented |
UL0204 # 01 Y:1998 | 01 | 1998 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $54,505 | $140,960 | Not Implemented |
UL0204 # 02 Y:1998 | 02 | 1998 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $162,300 | $0 | Not Implemented |
UL0204 # 03 Y:1998 | 03 | 1998 | ELIMINATE/REDUCE AN OPERATION | $5,360 | $0 | Not Implemented |
GT0645 # 01 Y:1998 | 01 | 1998 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $20,559 | $10,000 | Implemented |
GT0645 # 02 Y:1998 | 02 | 1998 | USE MINIMUM SAFE OVEN VENTILATION | $2,720 | $0 | Not Implemented |
GT0645 # 03 Y:1998 | 03 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,810 | $7,000 | Implemented |
GT0645 # 04 Y:1998 | 04 | 1998 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $34,362 | $22,000 | Implemented |
GT0645 # 05 Y:1998 | 05 | 1998 | PURCHASE MATERIAL FROM SUPPLIER IN CUSTOMIZED PACKAGING | $3,970 | $0 | Not Implemented |
GT0645 # 06 Y:1998 | 06 | 1998 | TREAT AND REUSE RINSE WATERS | $25,247 | $30,000 | Not Implemented |
ND0315 # 01 Y:1998 | 01 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,005 | $550 | Not Implemented |
ND0315 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $897 | $840 | Implemented |
ND0315 # 03 Y:1998 | 03 | 1998 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,863 | $1,000 | Implemented |
ND0315 # 04 Y:1998 | 04 | 1998 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $8,316 | $3,500 | Not Implemented |
ND0315 # 05 Y:1998 | 05 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $431 | $600 | Not Implemented |
ND0315 # 06 Y:1998 | 06 | 1998 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $4,840 | $2,500 | Not Implemented |