Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,485
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WM0140 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,092 | $0 | Implemented |
WM0140 # 08 Y:2019 | 08 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $637 | $510 | Not Implemented |
WM0140 # 09 Y:2019 | 09 | 2019 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $582 | $70 | Not Implemented |
IP0126 # 01 Y:2019 | 01 | 2019 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $19,811 | $0 | Not Implemented |
IP0126 # 02 Y:2019 | 02 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,594 | $0 | Not Implemented |
IP0126 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,500 | $125 | Not Implemented |
IP0126 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,865 | $93 | Not Implemented |
IP0126 # 05 Y:2019 | 05 | 2019 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $37,555 | $12,740 | Not Implemented |
IP0126 # 06 Y:2019 | 06 | 2019 | OPTIMIZE PLANT POWER FACTOR | $73,256 | $43,486 | Not Implemented |
IP0126 # 07 Y:2019 | 07 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,116 | $1,932 | Not Implemented |
IP0126 # 08 Y:2019 | 08 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,365 | $941 | Not Implemented |
IP0126 # 09 Y:2019 | 09 | 2019 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $1,752 | $1,356 | Not Implemented |
IP0126 # 10 Y:2019 | 10 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,441 | $2,582 | Not Implemented |
UD1001 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,285 | $4,400 | Implemented |
UD1001 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $705 | $1,200 | Implemented |
UD1001 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,497 | $16,508 | Implemented |
AM0786 # 01 Y:2019 | 01 | 2019 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $55,800 | $67,044 | Implemented |
AM0786 # 02 Y:2019 | 02 | 2019 | OPTIMIZE PLANT POWER FACTOR | $11,700 | $15,300 | Implemented |
AM0786 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,750 | $22,600 | Implemented |
AM0786 # 04 Y:2019 | 04 | 2019 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $2,760 | $4,570 | Implemented |
AM0786 # 05 Y:2019 | 05 | 2019 | USE SYNTHETIC LUBRICANT | $910 | $290 | Implemented |
SF0545 # 01 Y:2019 | 01 | 2019 | INSULATE BARE EQUIPMENT | $1,151 | $1,194 | Implemented |
SF0545 # 02 Y:2019 | 02 | 2019 | INSULATE BARE EQUIPMENT | $14,442 | $17,400 | Not Implemented |
SF0545 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,924 | $11,386 | Implemented |
SF0545 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,065 | $2,276 | Not Implemented |