Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,666
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0417 # 05 Y:2009 | 05 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,392 | $14,325 | Not Implemented |
SD0417 # 06 Y:2009 | 06 | 2009 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $43,985 | $8,096 | Not Implemented |
MA0652 # 01 Y:2009 | 01 | 2009 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $11,122 | $1,990 | Not Implemented |
MA0652 # 02 Y:2009 | 02 | 2009 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $10,132 | $23,474 | Implemented |
MA0652 # 03 Y:2009 | 03 | 2009 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,667 | $0 | Not Implemented |
MA0652 # 04 Y:2009 | 04 | 2009 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $3,585 | $6,600 | Not Implemented |
LL0315 # 01 Y:2009 | 01 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,024 | $4,200 | Implemented |
LL0315 # 02 Y:2009 | 02 | 2009 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,718 | $300 | Implemented |
LL0315 # 03 Y:2009 | 03 | 2009 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $641 | $927 | Not Implemented |
LL0315 # 04 Y:2009 | 04 | 2009 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $235 | $495 | Not Implemented |
LL0315 # 05 Y:2009 | 05 | 2009 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $193 | $1,020 | Implemented |
LL0315 # 06 Y:2009 | 06 | 2009 | INSTALL OCCUPANCY SENSORS | $61 | $240 | Not Implemented |
LL0315 # 07 Y:2009 | 07 | 2009 | INSULATE BARE EQUIPMENT | $44 | $177 | Not Implemented |
SD0416 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,133 | $35,628 | Implemented |
SD0416 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,893 | $5,295 | Implemented |
SD0416 # 03 Y:2009 | 03 | 2009 | USE PHOTOCELL CONTROLS | $3,458 | $4,950 | Implemented |
SD0416 # 04 Y:2009 | 04 | 2009 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $28,586 | $26,000 | Not Implemented |
SD0416 # 05 Y:2009 | 05 | 2009 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $655 | $0 | Implemented |
SD0416 # 06 Y:2009 | 06 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $485 | $0 | Implemented |
UW0032 # 05 Y:2009 | 05 | 2009 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $297 | $200 | Implemented |
UF0426 # 01 Y:2009 | 01 | 2009 | CLOSE OUTDOOR AIR DAMPERS DURING WARM-UP / COOL-DOWN PERIODS | $20,276 | $4,000 | Not Implemented |
UF0426 # 02 Y:2009 | 02 | 2009 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $146,810 | $3,192 | Not Implemented |
UF0426 # 03 Y:2009 | 03 | 2009 | RECYCLE FLUORESCENT LAMPS | $328 | $3,405 | Not Implemented |
UF0426 # 04 Y:2009 | 04 | 2009 | INSTALL SKYLIGHTS | $2,555 | $238 | Implemented |
UF0426 # 05 Y:2009 | 05 | 2009 | INSTALL OCCUPANCY SENSORS | $1,764 | $481 | Not Implemented |