Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,553
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0297 # 02 Y:1994 | 02 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,461 | $30 | Implemented |
MA0297 # 03 Y:1994 | 03 | 1994 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $3,339 | $5,980 | Not Implemented |
MA0297 # 04 Y:1994 | 04 | 1994 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $795 | $816 | Implemented |
MA0297 # 05 Y:1994 | 05 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $60 | $594 | Not Implemented |
MA0297 # 06 Y:1994 | 06 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $245 | $0 | Implemented |
MA0296 # 01 Y:1994 | 01 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $48,128 | $7,677 | Not Implemented |
MA0296 # 02 Y:1994 | 02 | 1994 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $11,136 | $10,870 | Not Implemented |
MA0296 # 03 Y:1994 | 03 | 1994 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $6,909 | $20,205 | Not Implemented |
MA0296 # 04 Y:1994 | 04 | 1994 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $3,525 | $7,280 | Not Implemented |
MA0296 # 05 Y:1994 | 05 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,714 | $0 | Implemented |
MA0296 # 06 Y:1994 | 06 | 1994 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,786 | $1,786 | Not Implemented |
MA0296 # 07 Y:1994 | 07 | 1994 | INSULATE BARE EQUIPMENT | $881 | $121 | Not Implemented |
MA0296 # 08 Y:1994 | 08 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $514 | $644 | Implemented |
MA0296 # 09 Y:1994 | 09 | 1994 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $303 | $688 | Not Implemented |
MA0293 # 01 Y:1994 | 01 | 1994 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $100,844 | $54,704 | Not Implemented |
MA0293 # 02 Y:1994 | 02 | 1994 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $21,561 | $34,000 | Not Implemented |
MA0293 # 03 Y:1994 | 03 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,149 | $644 | Implemented |
MA0293 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $491 | $100 | Implemented |
MA0293 # 05 Y:1994 | 05 | 1994 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,467 | $982 | Implemented |
MA0293 # 06 Y:1994 | 06 | 1994 | INSULATE BARE EQUIPMENT | $1,209 | $334 | Not Implemented |
MA0293 # 07 Y:1994 | 07 | 1994 | INSTALL OCCUPANCY SENSORS | $1,007 | $218 | Not Implemented |
MA0293 # 08 Y:1994 | 08 | 1994 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $769 | $0 | Implemented |
MA0293 # 09 Y:1994 | 09 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $739 | $0 | Implemented |
MA0293 # 10 Y:1994 | 10 | 1994 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $300 | $961 | Not Implemented |
MA0291 # 01 Y:1994 | 01 | 1994 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,823 | $6,000 | Not Implemented |