Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,553
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2312 # 10 Y:2023 | 10 | 2023 | ADOPT IN-HOUSE MATERIAL GENERATION | $54,436 | $125,322 | Not Implemented |
UC2312 # 09 Y:2023 | 09 | 2023 | INSULATE BARE EQUIPMENT | $445 | $390 | Not Implemented |
UC2312 # 08 Y:2023 | 08 | 2023 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $1,522 | $500 | Implemented |
UC2312 # 07 Y:2023 | 07 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,620 | $19,500 | Implemented |
UC2312 # 06 Y:2023 | 06 | 2023 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $1,947 | $9,514 | Not Implemented |
UC2312 # 05 Y:2023 | 05 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,710 | $1,062 | Implemented |
UC2312 # 04 Y:2023 | 04 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,573 | $75 | Implemented |
UC2312 # 03 Y:2023 | 03 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $6,502 | $150 | Implemented |
UC2312 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,426 | $1,300 | Implemented |
UC2312 # 01 Y:2023 | 01 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,161 | $428 | Not Implemented |
UC2311 # 11 Y:2023 | 11 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,083 | $4,561 | Implemented |
UC2311 # 01 Y:2023 | 01 | 2023 | PAY UTILITY BILLS ON TIME | $287 | $0 | Implemented |
UC2311 # 02 Y:2023 | 02 | 2023 | OPTIMIZE PLANT POWER FACTOR | $48,394 | $1,010 | Implemented |
UC2311 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,309 | $1,900 | Implemented |
UC2311 # 04 Y:2023 | 04 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,913 | $75 | Implemented |
UC2311 # 05 Y:2023 | 05 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $830 | $428 | Implemented |
UC2311 # 06 Y:2023 | 06 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $215 | $100 | Not Implemented |
UC2311 # 08 Y:2023 | 08 | 2023 | INSTALL TURBULATORS | $18,806 | $5,970 | Not Implemented |
UC2311 # 09 Y:2023 | 09 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,022 | $4,212 | Implemented |
UC2311 # 10 Y:2023 | 10 | 2023 | REPAIR AND ELIMINATE STEAM LEAKS | $2,564 | $1,995 | Implemented |
UC2311 # 12 Y:2023 | 12 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $95,417 | $1,401,053 | Not Implemented |
UC2311 # 13 Y:2023 | 13 | 2023 | USE BATTERY STORAGE FOR DEMAND CONTROL | $44,822 | $159,957 | Not Implemented |
UC2311 # 07 Y:2023 | 07 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $312 | $0 | Not Implemented |
UC2310 # 13 Y:2023 | 13 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $1,947 | $1,980 | Not Implemented |
UC2310 # 12 Y:2023 | 12 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $791 | $1,804 | Not Implemented |