Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,880
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CI0020 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $76,570 | $180,000 | n/a |
CI0020 # 03 Y:2023 | 03 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $55,349 | $45,000 | n/a |
CI0020 # 04 Y:2023 | 04 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,503 | $2,870 | n/a |
CI0020 # 05 Y:2023 | 05 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,187 | $20,000 | n/a |
CI0020 # 06 Y:2023 | 06 | 2023 | USE PHOTOCELL CONTROLS | $1,246 | $750 | n/a |
CM1024 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $28,381 | $291,962 | n/a |
CM1024 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,939 | $6,474 | n/a |
CM1024 # 03 Y:2023 | 03 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,832 | $36,480 | n/a |
CM1024 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $843 | $17,694 | n/a |
CM1024 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $760 | $75 | n/a |
CM1024 # 06 Y:2023 | 06 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,011 | $8,000 | n/a |
GT0970 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $37,757 | $200 | Implemented |
GT0970 # 02 Y:2023 | 02 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,613 | $75 | Implemented |
GT0970 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,675 | $1,850 | Implemented |
GT0970 # 04 Y:2023 | 04 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $268 | $456 | Not Implemented |
GT0970 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $93,953 | $385,000 | Implemented |
GT0970 # 06 Y:2023 | 06 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $70,120 | $1,934,090 | Not Implemented |
DL0226 # 01 Y:2023 | 01 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,718 | $0 | Implemented |
DL0226 # 02 Y:2023 | 02 | 2023 | REDUCE VENTILATION AIR | $1,234 | $0 | Implemented |
DL0226 # 03 Y:2023 | 03 | 2023 | ADJUST VENTS TO MINIMIZE ENERGY USE | $2,053 | $0 | Implemented |
DL0226 # 04 Y:2023 | 04 | 2023 | REDUCE VENTILATION AIR | $2,739 | $0 | Not Implemented |
DL0226 # 05 Y:2023 | 05 | 2023 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $4,421 | $3,000 | Not Implemented |
DL0226 # 06 Y:2023 | 06 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $12,451 | $0 | Implemented |
DL0226 # 07 Y:2023 | 07 | 2023 | REDUCE VENTILATION AIR | $1,643 | $57 | Implemented |
DL0226 # 08 Y:2023 | 08 | 2023 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $6,284 | $3,000 | Not Implemented |