Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,317
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0280 # 10 Y:2003 | 10 | 2003 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,633 | $0 | Not Implemented |
WV0280 # 11 Y:2003 | 11 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,080 | $477 | Implemented |
WV0280 # 12 Y:2003 | 12 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,953 | $7,230 | Implemented |
WV0274 # 01 Y:2003 | 01 | 2003 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $22,034 | $1,640 | Not Implemented |
WV0274 # 02 Y:2003 | 02 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,198 | $1,000 | Implemented |
WV0274 # 03 Y:2003 | 03 | 2003 | MAINTAIN MACHINES TO REDUCE LEAKS | $5,774 | $35 | Implemented |
WV0274 # 04 Y:2003 | 04 | 2003 | INSULATE BARE EQUIPMENT | $3,173 | $252 | Implemented |
WV0274 # 05 Y:2003 | 05 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,432 | $2,093 | Not Implemented |
WV0274 # 06 Y:2003 | 06 | 2003 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $1,068 | $435 | Implemented |
WV0274 # 07 Y:2003 | 07 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $772 | $2,925 | Implemented |
WV0274 # 08 Y:2003 | 08 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $654 | $73 | Implemented |
WV0274 # 09 Y:2003 | 09 | 2003 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $26 | $0 | Implemented |
WV0270 # 01 Y:2003 | 01 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,616 | $0 | Implemented |
WV0270 # 02 Y:2003 | 02 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,533 | $0 | Implemented |
WV0270 # 03 Y:2003 | 03 | 2003 | DEVELOP A REPAIR/REPLACE POLICY | $6,214 | $625 | Implemented |
WV0270 # 04 Y:2003 | 04 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $5,034 | $250 | Not Implemented |
WV0270 # 05 Y:2003 | 05 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,121 | $150 | Implemented |
WV0270 # 06 Y:2003 | 06 | 2003 | INSULATE BARE EQUIPMENT | $7,108 | $1,418 | Implemented |
WV0270 # 07 Y:2003 | 07 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,894 | $500 | Not Implemented |
WV0270 # 08 Y:2003 | 08 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,379 | $810 | Not Implemented |
WV0270 # 09 Y:2003 | 09 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,937 | $250 | Implemented |
WV0270 # 10 Y:2003 | 10 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,296 | $735 | Not Implemented |
WV0270 # 11 Y:2003 | 11 | 2003 | INSTALL OCCUPANCY SENSORS | $2,244 | $1,450 | Implemented |
WV0270 # 12 Y:2003 | 12 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,750 | $4,590 | Implemented |
WV0270 # 13 Y:2003 | 13 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,088 | $2,000 | Not Implemented |