Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,230
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0844 # 05 Y:2011 | 05 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,557 | $0 | Implemented |
UD0844 # 06 Y:2011 | 06 | 2011 | UPGRADE CONTROLS ON COMPRESSORS | $20,051 | $18,555 | Not Implemented |
UD0844 # 07 Y:2011 | 07 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,542 | $0 | Not Implemented |
UD0844 # 08 Y:2011 | 08 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,988 | $5,000 | Not Implemented |
UD0844 # 09 Y:2011 | 09 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,616 | $500 | Not Implemented |
UD0844 # 10 Y:2011 | 10 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $267 | $0 | Implemented |
UD0844 # 11 Y:2011 | 11 | 2011 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $13,123 | $1,000 | Implemented |
UD0844 # 12 Y:2011 | 12 | 2011 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $10,508 | $16,000 | Not Implemented |
UD0844 # 13 Y:2011 | 13 | 2011 | USE OPTIMUM TEMPERATURE | $3,225 | $0 | Not Implemented |
UD0844 # 14 Y:2011 | 14 | 2011 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $18,762 | $0 | Implemented |
UD0844 # 15 Y:2011 | 15 | 2011 | REDUCE VENTILATION AIR | $17,779 | $0 | Not Implemented |
TT0083 # 01 Y:2011 | 01 | 2011 | OPTIMIZE PLANT POWER FACTOR | $9,142 | $15,000 | Implemented |
TT0083 # 02 Y:2011 | 02 | 2011 | INSTALL SKYLIGHTS | $2,883 | $36,500 | Not Implemented |
TT0083 # 03 Y:2011 | 03 | 2011 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $14,378 | $1,200 | Implemented |
TT0083 # 04 Y:2011 | 04 | 2011 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $337 | $29,076 | Not Implemented |
TT0083 # 05 Y:2011 | 05 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $267 | $1,370 | Not Implemented |
TT0083 # 06 Y:2011 | 06 | 2011 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $5,312 | $3,825 | Not Implemented |
MS0384 # 01 Y:2011 | 01 | 2011 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $6,041 | $1,900 | Not Implemented |
MS0384 # 02 Y:2011 | 02 | 2011 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $3,680 | $611 | Not Implemented |
MS0384 # 03 Y:2011 | 03 | 2011 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,101 | $13,781 | Not Implemented |
MA0683 # 01 Y:2011 | 01 | 2011 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $24,679 | $50,000 | Not Implemented |
MA0683 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,021 | $2,800 | Implemented |
MA0683 # 03 Y:2011 | 03 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,273 | $200 | Implemented |
MA0683 # 04 Y:2011 | 04 | 2011 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $1,113 | $200 | Implemented |
MA0683 # 05 Y:2011 | 05 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $821 | $200 | Implemented |