IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,754

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0743 # 05 Y:2007 05 2007 INSTALL OCCUPANCY SENSORS $21,613 $2,450 Implemented
OK0743 # 06 Y:2007 06 2007 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $24,607 $0 Not Implemented
OK0743 # 07 Y:2007 07 2007 INSULATE BARE EQUIPMENT $5,413 $723 Implemented
OK0741 # 01 Y:2007 01 2007 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $144,120 $500,000 Not Implemented
OK0741 # 02 Y:2007 02 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,666 $860 Not Implemented
OK0741 # 03 Y:2007 03 2007 RECOVER WASTE HEAT FROM EQUIPMENT $8,334 $7,480 Not Implemented
OK0741 # 04 Y:2007 04 2007 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $2,042 $6,800 Not Implemented
OK0741 # 05 Y:2007 05 2007 INSTALL SET-BACK TIMERS $273 $248 Not Implemented
OK0739 # 01 Y:2006 01 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,798 $9,750 Implemented
OK0739 # 02 Y:2006 02 2006 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $156,872 $2,175,000 Not Implemented
OK0739 # 03 Y:2006 03 2006 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $139,230 $39,852 Not Implemented
OK0739 # 04 Y:2006 04 2006 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $3,011 $390 Not Implemented
OK0739 # 05 Y:2006 05 2006 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $5,090 $7,944 Implemented
OK0739 # 06 Y:2006 06 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,587 $191 Implemented
OK0739 # 07 Y:2006 07 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,734 $9,485 Not Implemented
OK0737 # 01 Y:2006 01 2006 USE MINIMUM STEAM OPERATING PRESSURE $22,707 $1,420 Not Implemented
OK0737 # 02 Y:2006 02 2006 INCREASE AMOUNT OF CONDENSATE RETURNED $7,798 $11,625 Not Implemented
OK0737 # 03 Y:2006 03 2006 REPAIR OR REPLACE STEAM TRAPS $92,687 $1,025 Not Implemented
OK0737 # 04 Y:2006 04 2006 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $30,440 $19,260 Not Implemented
OK0737 # 05 Y:2006 05 2006 MODERATE COOLING TOWER OUTLET TEMPERATURE $28,248 $15,000 Not Implemented
OK0735 # 01 Y:2006 01 2006 REDUCE EXCESSIVE BOILER BLOWDOWN $69,788 $55,933 Not Implemented
OK0735 # 02 Y:2006 02 2006 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $13,821 $9,500 Not Implemented
OK0735 # 03 Y:2006 03 2006 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $29,625 $4,000 Not Implemented
OK0735 # 04 Y:2006 04 2006 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $8,193 $12,830 Not Implemented
OK0735 # 05 Y:2006 05 2006 INSTALL / REPAIR INSULATION ON STEAM LINES $1,240 $700 Not Implemented