Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,872
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AR0145 # 04 Y:1998 | 04 | 1998 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $627 | $1,105 | Implemented |
AR0145 # 05 Y:1998 | 05 | 1998 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $718 | $500 | Implemented |
AR0145 # 06 Y:1998 | 06 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $166 | $458 | Implemented |
AR0145 # 07 Y:1998 | 07 | 1998 | ELIMINATE PRACTICE OF MIXING WASTE STREAMS | $2,463 | $500 | Not Implemented |
AR0145 # 08 Y:1998 | 08 | 1998 | RECYCLE CLEANING SOLVENT AND REUSE | $663 | $100 | Not Implemented |
AR0145 # 09 Y:1998 | 09 | 1998 | INCREASE USE OF AUTOMATION | $73,428 | $8,200 | Implemented |
SD0209 # 01 Y:1998 | 01 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $177,242 | $44,000 | Not Implemented |
SD0209 # 02 Y:1998 | 02 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $5,718 | $2,500 | Not Implemented |
SD0209 # 03 Y:1998 | 03 | 1998 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $1,717 | $1,000 | Not Implemented |
SD0209 # 04 Y:1998 | 04 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,228 | $0 | Implemented |
SD0209 # 05 Y:1998 | 05 | 1998 | USE A RAG RECYCLE SERVICE | $10,318 | $1,200 | Implemented |
SD0209 # 06 Y:1998 | 06 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $331,304 | $21,000 | Not Implemented |
SD0209 # 07 Y:1998 | 07 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $108,568 | $13,000 | Not Implemented |
SD0209 # 08 Y:1998 | 08 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $22,000 | $0 | Not Implemented |
SD0209 # 09 Y:1998 | 09 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $89,794 | $81,000 | Not Implemented |
SD0209 # 10 Y:1998 | 10 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $10,300 | $8,000 | Not Implemented |
OR0324 # 01 Y:1998 | 01 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $300,000 | $178,750 | Not Implemented |
OR0324 # 02 Y:1998 | 02 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $88,020 | $60,000 | Not Implemented |
OR0324 # 03 Y:1998 | 03 | 1998 | REDUCE SCRAP PRODUCTION | $34,430 | $11,000 | Not Implemented |
OR0324 # 04 Y:1998 | 04 | 1998 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $11,110 | $42,200 | Not Implemented |
OR0324 # 05 Y:1998 | 05 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $5,950 | $800 | Not Implemented |
OR0324 # 06 Y:1998 | 06 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,935 | $2,000 | Implemented |
OR0324 # 07 Y:1998 | 07 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,860 | $3,700 | Implemented |
OR0324 # 08 Y:1998 | 08 | 1998 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,460 | $1,060 | Implemented |
MO0237 # 01 Y:1998 | 01 | 1998 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,858 | $4,700 | Implemented |