Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,304
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0557 # 05 Y:2010 | 05 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,655 | $1,655 | Not Implemented |
OR0557 # 06 Y:2010 | 06 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,035 | $3,858 | Not Implemented |
OR0557 # 07 Y:2010 | 07 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,471 | $1,471 | Not Implemented |
OR0557 # 08 Y:2010 | 08 | 2010 | INSTALL / REPAIR INSULATION ON STEAM LINES | $615 | $353 | Not Implemented |
OR0557 # 09 Y:2010 | 09 | 2010 | USE SOLAR HEAT TO MAKE ELECTRICTY | $23,079 | $87,827 | Not Implemented |
SF0387 # 01 Y:2010 | 01 | 2010 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $5,144 | $0 | Not Implemented |
SF0387 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $747 | $0 | Implemented |
SF0387 # 03 Y:2010 | 03 | 2010 | USE PHOTOCELL CONTROLS | $7,756 | $1,353 | Implemented |
SF0387 # 04 Y:2010 | 04 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,874 | $1,627 | Implemented |
SF0387 # 05 Y:2010 | 05 | 2010 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,964 | $7,727 | Implemented |
SF0387 # 06 Y:2010 | 06 | 2010 | USE OPTIMUM THICKNESS INSULATION | $791 | $1,536 | Implemented |
SF0387 # 07 Y:2010 | 07 | 2010 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $397 | $798 | Implemented |
SF0387 # 08 Y:2010 | 08 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,393 | $2,851 | Implemented |
SF0387 # 09 Y:2010 | 09 | 2010 | INSTALL OCCUPANCY SENSORS | $920 | $2,132 | Implemented |
SF0387 # 10 Y:2010 | 10 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,160 | $3,840 | Implemented |
SF0387 # 11 Y:2010 | 11 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,342 | $6,259 | Implemented |
MI0191 # 01 Y:2010 | 01 | 2010 | HEAT WATER WITH EXHAUST HEAT | $697,331 | $128,000 | Not Implemented |
MI0191 # 02 Y:2010 | 02 | 2010 | USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS | $228,145 | $400,000 | Not Implemented |
MI0191 # 03 Y:2010 | 03 | 2010 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $48,196 | $1,500 | Not Implemented |
MI0191 # 04 Y:2010 | 04 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $47,683 | $1,210 | Implemented |
MI0191 # 05 Y:2010 | 05 | 2010 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $8,572 | $5,300 | Implemented |
DL0055 # 01 Y:2010 | 01 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $31,870 | $13,000 | Not Implemented |
DL0055 # 02 Y:2010 | 02 | 2010 | REPLACE BOILER | $59,500 | $102,000 | Not Implemented |
DL0055 # 03 Y:2010 | 03 | 2010 | OPERATE BOILERS ON HIGH FIRE SETTING | $35,000 | $50 | Not Implemented |
DL0055 # 04 Y:2010 | 04 | 2010 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $39,150 | $100,000 | Not Implemented |