Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,874
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0432 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $380 | $50 | Not Implemented |
CO0432 # 04 Y:1999 | 04 | 1999 | USE LOW VOC OR WATER BASED PAINT | $10,460 | $5,000 | Not Implemented |
CO0432 # 05 Y:1999 | 05 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $3,230 | $2,500 | Not Implemented |
CO0432 # 06 Y:1999 | 06 | 1999 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $1,470 | $3,000 | Not Implemented |
CO0431 # 01 Y:1999 | 01 | 1999 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $16,420 | $21,500 | Implemented |
CO0431 # 02 Y:1999 | 02 | 1999 | INSTALL TURBULATORS | $1,830 | $3,630 | Implemented |
CO0431 # 03 Y:1999 | 03 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,340 | $610 | Implemented |
CO0431 # 04 Y:1999 | 04 | 1999 | MAKE A NEW BY-PRODUCT | $4,350 | $19,100 | Not Implemented |
CO0431 # 05 Y:1999 | 05 | 1999 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $370 | $0 | Not Implemented |
CO0431 # 06 Y:1999 | 06 | 1999 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $638,100 | $0 | Implemented |
CO0431 # 07 Y:1999 | 07 | 1999 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $44,640 | $0 | Implemented |
CO0430 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,060 | $12,077 | Implemented |
CO0430 # 02 Y:1998 | 02 | 1998 | INSTALL TURBULATORS | $1,770 | $5,750 | Not Implemented |
CO0430 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,470 | $1,280 | Implemented |
CO0430 # 04 Y:1998 | 04 | 1998 | USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS | $-210 | $2,000 | Implemented |
CO0430 # 05 Y:1998 | 05 | 1998 | SELL COMBUSTIBLE WASTE | $15,970 | $56,700 | Implemented |
CO0430 # 06 Y:1998 | 06 | 1998 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $674,900 | $1,645,000 | Not Implemented |
CO0429 # 01 Y:1998 | 01 | 1998 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $840 | $1,000 | Implemented |
CO0429 # 02 Y:1998 | 02 | 1998 | CLOSELY MONITOR CHEMICAL ADDITIONS TO INCREASE BATH LIFE | $4,860 | $0 | Implemented |
CO0429 # 03 Y:1998 | 03 | 1998 | ALLOW DRAINAGE BEFORE WITHDRAWING OBJECT | $2,930 | $800 | Not Implemented |
CO0429 # 04 Y:1998 | 04 | 1998 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $6,000 | $10,160 | Implemented |
CO0429 # 05 Y:1998 | 05 | 1998 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $730 | $280 | Not Implemented |
CO0428 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,428 | $8,036 | Not Implemented |
CO0428 # 02 Y:1998 | 02 | 1998 | DISCONNECT BALLASTS | $3,050 | $350 | Not Implemented |
CO0428 # 03 Y:1998 | 03 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $470 | $50 | Not Implemented |