Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,260
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0526 # 04 Y:2007 | 04 | 2007 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $18,200 | $30,000 | Implemented |
OR0526 # 05 Y:2007 | 05 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,600 | $2,600 | Implemented |
OR0526 # 06 Y:2007 | 06 | 2007 | UPGRADE CONTROLS ON COMPRESSORS | $8,800 | $800 | Not Implemented |
OR0526 # 07 Y:2007 | 07 | 2007 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,400 | $3,800 | Implemented |
BD0337 # 01 Y:2007 | 01 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $927 | $1,115 | Not Implemented |
BD0337 # 02 Y:2007 | 02 | 2007 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $14,425 | $480 | Implemented |
BD0337 # 03 Y:2007 | 03 | 2007 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,084 | $2,150 | Not Implemented |
BD0337 # 04 Y:2007 | 04 | 2007 | USE SYNTHETIC LUBRICANT | $228 | $601 | Not Implemented |
BD0337 # 05 Y:2007 | 05 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $926 | $2 | Not Implemented |
DL0009 # 01 Y:2007 | 01 | 2007 | INSTALL / REPAIR INSULATION ON STEAM LINES | $28,059 | $10,000 | Implemented |
DL0009 # 02 Y:2007 | 02 | 2007 | REDESIGN PROCESS | $15,567 | $6,300 | Not Implemented |
DL0009 # 03 Y:2007 | 03 | 2007 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $11,200 | $60,000 | Not Implemented |
DL0009 # 04 Y:2007 | 04 | 2007 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $10,793 | $11,313 | Not Implemented |
DL0009 # 05 Y:2007 | 05 | 2007 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,192 | $50,000 | Implemented |
DL0009 # 06 Y:2007 | 06 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,454 | $0 | Not Implemented |
DL0009 # 07 Y:2007 | 07 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,890 | $695 | Implemented |
DL0009 # 08 Y:2007 | 08 | 2007 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,941 | $590 | Not Implemented |
DL0009 # 09 Y:2007 | 09 | 2007 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,924 | $3,809 | Implemented |
DL0009 # 10 Y:2007 | 10 | 2007 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $4,500 | $4,968 | Not Implemented |
DL0009 # 11 Y:2007 | 11 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,550 | $20,000 | Implemented |
DL0009 # 12 Y:2007 | 12 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $310 | $160 | Not Implemented |
DL0009 # 13 Y:2007 | 13 | 2007 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $302 | $10,000 | Implemented |
DL0009 # 14 Y:2007 | 14 | 2007 | USE SOLAR HEAT TO MAKE ELECTRICTY | $20,475 | $1,275,000 | Not Implemented |
MZ0018 # 01 Y:2007 | 01 | 2007 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $25,600 | $0 | Not Implemented |
MZ0018 # 02 Y:2007 | 02 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,872 | $0 | Not Implemented |