Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,737
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0236 # 05 Y:2020 | 05 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,447 | $15,750 | Not Implemented |
TT0236 # 06 Y:2020 | 06 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,574 | $40 | Not Implemented |
TT0236 # 07 Y:2020 | 07 | 2020 | CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | $1,908 | $500 | Not Implemented |
TT0236 # 08 Y:2020 | 08 | 2020 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $1,653 | $2,150 | Not Implemented |
TT0236 # 09 Y:2020 | 09 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $984 | $1,500 | Not Implemented |
TT0236 # 10 Y:2020 | 10 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $206 | $450 | Not Implemented |
SF0552 # 01 Y:2020 | 01 | 2020 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $25,284 | $0 | Not Implemented |
SF0552 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,516 | $0 | Implemented |
SF0552 # 03 Y:2020 | 03 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $575 | $137 | Implemented |
SF0552 # 04 Y:2020 | 04 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $896 | $400 | Implemented |
SF0552 # 05 Y:2020 | 05 | 2020 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,065 | $1,862 | Implemented |
SF0552 # 06 Y:2020 | 06 | 2020 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $10,077 | $12,392 | Not Implemented |
SF0552 # 07 Y:2020 | 07 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,621 | $33,085 | Implemented |
SF0552 # 08 Y:2020 | 08 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $88,458 | $451,750 | Implemented |
WM0156 # 01 Y:2020 | 01 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $20,527 | $105,000 | Not Implemented |
WM0156 # 02 Y:2020 | 02 | 2020 | USE SYNTHETIC LUBRICANT | $11,563 | $3,300 | Not Implemented |
WM0156 # 03 Y:2020 | 03 | 2020 | SHUT OFF AIR CONDITIONING IN WINTER HEATING SEASON | $9,593 | $0 | Not Implemented |
WM0156 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,847 | $13,133 | Not Implemented |
WM0156 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,864 | $3,527 | Implemented |
WM0156 # 06 Y:2020 | 06 | 2020 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,164 | $0 | Implemented |
WM0156 # 07 Y:2020 | 07 | 2020 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $1,144 | $4,600 | Not Implemented |
WM0156 # 08 Y:2020 | 08 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,058 | $0 | Not Implemented |
WM0156 # 09 Y:2020 | 09 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $554 | $2,225 | Not Implemented |
WM0156 # 10 Y:2020 | 10 | 2020 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $542 | $1,785 | Not Implemented |
OR0735 # 01 Y:2020 | 01 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $5,347 | $1,090 | Implemented |