Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,314
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0283 # 10 Y:2000 | 10 | 2000 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $3,750 | $8,000 | Not Implemented |
AS0283 # 11 Y:2000 | 11 | 2000 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $6,626 | $1,300 | Not Implemented |
AS0282 # 01 Y:2000 | 01 | 2000 | ADD AREA LIGHTING SWITCHES | $3,618 | $2,270 | Not Implemented |
AS0282 # 02 Y:2000 | 02 | 2000 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $959 | $120 | Implemented |
AS0282 # 03 Y:2000 | 03 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $697 | $536 | Implemented |
AS0282 # 04 Y:2000 | 04 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,563 | $60 | Implemented |
AS0282 # 05 Y:2000 | 05 | 2000 | USE SYNTHETIC LUBRICANT | $1,793 | $694 | Not Implemented |
AS0282 # 06 Y:2000 | 06 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,843 | $4,974 | Implemented |
AS0282 # 07 Y:2000 | 07 | 2000 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $2,580 | $120 | Implemented |
AS0282 # 08 Y:2000 | 08 | 2000 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $624 | $60 | Implemented |
AS0282 # 09 Y:2000 | 09 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $292,414 | $1,000,000 | Not Implemented |
AS0281 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $895 | $2,709 | Not Implemented |
AS0281 # 02 Y:2000 | 02 | 2000 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $581 | $600 | Not Implemented |
AS0281 # 03 Y:2000 | 03 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,825 | $3,713 | Not Implemented |
AS0281 # 04 Y:2000 | 04 | 2000 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,723 | $4,950 | Not Implemented |
AS0281 # 05 Y:2000 | 05 | 2000 | USE EVAPORATION TO CONCENTRATE MATERIAL | $8,037 | $8,525 | Implemented |
AS0281 # 06 Y:2000 | 06 | 2000 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $456 | $60 | Implemented |
AS0281 # 07 Y:2000 | 07 | 2000 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $4,476 | $60 | Not Implemented |
AS0281 # 08 Y:2000 | 08 | 2000 | MODIFY STARTUP/SHUTDOWN TIMES | $8,782 | $9,600 | Not Implemented |
AS0281 # 09 Y:2000 | 09 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $31,250 | $15,000 | Not Implemented |
AS0280 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,109 | $12,163 | Implemented |
AS0280 # 02 Y:2000 | 02 | 2000 | INSTALL OCCUPANCY SENSORS | $1,996 | $2,925 | Not Implemented |
AS0280 # 03 Y:2000 | 03 | 2000 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,658 | $1,605 | Implemented |
AS0280 # 04 Y:2000 | 04 | 2000 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $16,673 | $30,000 | Implemented |
AS0280 # 05 Y:2000 | 05 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,337 | $1,066 | Implemented |