Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,642
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0034 # 06 Y:2009 | 06 | 2009 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $39,780 | $3,000 | Not Implemented |
MZ0034 # 07 Y:2009 | 07 | 2009 | USE SMALL NUMBER OF HIGH OUTPUT UNITS INSTEAD OF MANY SMALL INEFFICIENT UNITS | $13,376 | $20,000 | Implemented |
MZ0033 # 01 Y:2009 | 01 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,783 | $990 | Not Implemented |
MZ0033 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,040 | $46,900 | Implemented |
MZ0033 # 03 Y:2009 | 03 | 2009 | INSTALL OCCUPANCY SENSORS | $169 | $178 | Implemented |
MZ0033 # 04 Y:2009 | 04 | 2009 | INSTALL OCCUPANCY SENSORS | $259 | $178 | Implemented |
MZ0033 # 05 Y:2009 | 05 | 2009 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $13,936 | $400 | Implemented |
MZ0033 # 06 Y:2009 | 06 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,579 | $8,000 | Not Implemented |
MZ0032 # 01 Y:2008 | 01 | 2008 | INSTALL OCCUPANCY SENSORS | $1,456 | $712 | Implemented |
MZ0032 # 02 Y:2008 | 02 | 2008 | INSTALL OCCUPANCY SENSORS | $651 | $356 | Not Implemented |
MZ0032 # 03 Y:2008 | 03 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $703 | $0 | Implemented |
MZ0032 # 04 Y:2008 | 04 | 2008 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $757 | $300 | Implemented |
MZ0029 # 01 Y:2008 | 01 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $7,405 | $900 | Not Implemented |
MZ0029 # 02 Y:2008 | 02 | 2008 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,047 | $0 | Not Implemented |
MZ0029 # 03 Y:2008 | 03 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,216 | $900 | Not Implemented |
MZ0029 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $32,075 | $43,400 | Implemented |
MZ0029 # 05 Y:2008 | 05 | 2008 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $6 | $20 | Implemented |
MZ0024 # 01 Y:2008 | 01 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $764 | $900 | Implemented |
MZ0024 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $27,181 | $32,800 | Implemented |
MZ0024 # 03 Y:2008 | 03 | 2008 | SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING | $828 | $370 | Not Implemented |
MZ0024 # 04 Y:2008 | 04 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,506 | $5,600 | Not Implemented |
MZ0024 # 05 Y:2008 | 05 | 2008 | USE OPTIMUM THICKNESS INSULATION | $430 | $800 | Not Implemented |
MZ0028 # 01 Y:2008 | 01 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $723 | $500 | Not Implemented |
MZ0028 # 02 Y:2008 | 02 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $30,107 | $6,000 | Not Implemented |
MZ0028 # 03 Y:2008 | 03 | 2008 | USE OPTIMUM THICKNESS INSULATION | $457 | $500 | Implemented |