IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,043

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0884 # 05 Y:2013 05 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $936 $500 Implemented
UD0884 # 06 Y:2013 06 2013 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $6,058 $500 Implemented
UD0884 # 07 Y:2013 07 2013 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $7,470 $0 Implemented
UD0884 # 08 Y:2013 08 2013 UTILIZE A LESS EXPENSIVE COOLING METHOD $8,876 $0 Implemented
UD0884 # 09 Y:2013 09 2013 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $2,533 $2,000 Implemented
UD0884 # 10 Y:2013 10 2013 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $2,365 $11,824 Implemented
UD0884 # 11 Y:2013 11 2013 AVOID FROST FORMATION ON EVAPORATORS $1,417 $0 Implemented
UD0884 # 12 Y:2013 12 2013 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $1,101 $0 Implemented
NC0485 # 01 Y:2013 01 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $35,649 $108,665 Implemented
NC0485 # 02 Y:2013 02 2013 INSTALL OCCUPANCY SENSORS $2,016 $7,315 Implemented
NC0485 # 03 Y:2013 03 2013 USE PHOTOCELL CONTROLS $2,647 $3,750 Implemented
NC0485 # 04 Y:2013 04 2013 REPAIR OR REPLACE STEAM TRAPS $167,046 $6,100 Implemented
NC0485 # 05 Y:2013 05 2013 INSTALL / REPAIR INSULATION ON STEAM LINES $2,936 $300 Not Implemented
NC0485 # 06 Y:2013 06 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $17,809 $100 Implemented
NC0485 # 07 Y:2013 07 2013 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $148,178 $100,000 Not Implemented
NC0485 # 08 Y:2013 08 2013 RECOVER WASTE HEAT FROM EQUIPMENT $22,938 $75,000 Not Implemented
SD0469 # 01 Y:2013 01 2013 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $37,421 $53,250 Implemented
SD0469 # 02 Y:2013 02 2013 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $23,156 $8,740 Not Implemented
SD0469 # 03 Y:2013 03 2013 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $15,384 $50,200 Not Implemented
SD0469 # 04 Y:2013 04 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,246 $10,350 Not Implemented
SD0469 # 05 Y:2013 05 2013 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $10,014 $15,500 Not Implemented
SD0469 # 06 Y:2013 06 2013 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $7,769 $7,320 Not Implemented
SD0469 # 07 Y:2013 07 2013 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $3,825 $1,500 Not Implemented
SD0469 # 08 Y:2013 08 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,817 $600 Not Implemented
SD0469 # 09 Y:2013 09 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,250 $200 Implemented