Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,666
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0352 # 03 Y:2009 | 03 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,300 | $1,700 | Implemented |
UM0352 # 04 Y:2009 | 04 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,569 | $1,060 | Not Implemented |
UM0352 # 05 Y:2009 | 05 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,200 | $0 | Implemented |
UM0352 # 06 Y:2009 | 06 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,800 | $1,900 | Not Implemented |
UM0352 # 07 Y:2009 | 07 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,454 | $0 | Implemented |
UM0352 # 08 Y:2009 | 08 | 2009 | INSTALL OCCUPANCY SENSORS | $504 | $920 | Implemented |
UM0352 # 09 Y:2009 | 09 | 2009 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,944 | $1,200 | Implemented |
UM0351 # 01 Y:2009 | 01 | 2009 | TURN OFF EQUIPMENT WHEN NOT IN USE | $37,050 | $0 | Implemented |
UM0351 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,706 | $19,921 | Implemented |
UM0351 # 03 Y:2009 | 03 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,516 | $100 | Not Implemented |
UM0351 # 04 Y:2009 | 04 | 2009 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,124 | $2,800 | Not Implemented |
UM0351 # 05 Y:2009 | 05 | 2009 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,656 | $500 | Implemented |
UM0351 # 06 Y:2009 | 06 | 2009 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,506 | $1,660 | Not Implemented |
IC0154 # 07 Y:2009 | 07 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $220 | $460 | Not Implemented |
IC0154 # 08 Y:2009 | 08 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $87 | $0 | Not Implemented |
IC0154 # 09 Y:2009 | 09 | 2009 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $725 | $1,126 | Not Implemented |
IC0154 # 10 Y:2009 | 10 | 2009 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,269 | $0 | Not Implemented |
IC0154 # 11 Y:2009 | 11 | 2009 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $2,094 | $0 | Not Implemented |
NC0387 # 01 Y:2009 | 01 | 2009 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $202,240 | $400,000 | Not Implemented |
NC0387 # 02 Y:2009 | 02 | 2009 | MAKE ICE DURING OFF PEAK HOURS FOR COOLING | $51,343 | $72,000 | Not Implemented |
NC0387 # 03 Y:2009 | 03 | 2009 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $44,613 | $45,000 | Not Implemented |
NC0387 # 04 Y:2009 | 04 | 2009 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $21,000 | $25,000 | Not Implemented |
NC0387 # 05 Y:2009 | 05 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,105 | $7,000 | Not Implemented |
NC0387 # 06 Y:2009 | 06 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,447 | $100 | Implemented |
NC0387 # 07 Y:2009 | 07 | 2009 | DEVELOP A REPAIR/REPLACE POLICY | $2,019 | $2,198 | Not Implemented |