Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,043
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0860 # 10 Y:2013 | 10 | 2013 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $14,580 | $12,694 | Not Implemented |
OK0860 # 11 Y:2013 | 11 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $32,972 | $69,860 | Not Implemented |
OK0860 # 12 Y:2013 | 12 | 2013 | INSTALL OCCUPANCY SENSORS | $445 | $3,675 | Implemented |
MA0712 # 01 Y:2013 | 01 | 2013 | USE RADIANT HEATER FOR SPOT HEATING | $13,420 | $65,327 | Implemented |
MA0712 # 02 Y:2013 | 02 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,863 | $12,000 | Implemented |
MA0712 # 03 Y:2013 | 03 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,311 | $5,000 | Implemented |
MA0712 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,440 | $4,200 | Not Implemented |
MA0712 # 05 Y:2013 | 05 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $938 | $2,930 | Not Implemented |
MA0712 # 06 Y:2013 | 06 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $853 | $2,930 | Not Implemented |
MA0712 # 07 Y:2013 | 07 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $827 | $1,200 | Implemented |
MA0712 # 08 Y:2013 | 08 | 2013 | INSULATE BARE EQUIPMENT | $323 | $750 | Implemented |
BS0018 # 01 Y:2013 | 01 | 2013 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $552 | $934 | Implemented |
BS0018 # 02 Y:2013 | 02 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,122 | $7,317 | Implemented |
BS0018 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $152 | $600 | Implemented |
BS0018 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,152 | $3,300 | Not Implemented |
BS0018 # 05 Y:2013 | 05 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $432 | $718 | Not Implemented |
BD0429 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,975 | $200 | Implemented |
BD0429 # 02 Y:2013 | 02 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,306 | $5,680 | Not Implemented |
BD0429 # 03 Y:2013 | 03 | 2013 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,152 | $30 | Not Implemented |
BD0429 # 04 Y:2013 | 04 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $666 | $25 | Not Implemented |
BD0429 # 05 Y:2013 | 05 | 2013 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $651 | $2,300 | Not Implemented |
BD0429 # 06 Y:2013 | 06 | 2013 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $354 | $440 | Not Implemented |
BD0429 # 07 Y:2013 | 07 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $226 | $700 | Not Implemented |
IA0499 # 01 Y:2013 | 01 | 2013 | OPTIMIZE PLANT POWER FACTOR | $7,492 | $3,371 | Not Implemented |
IA0499 # 02 Y:2013 | 02 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,315 | $700 | Not Implemented |