Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,708
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LM0039 # 06 Y:2002 | 06 | 2002 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $20,000 | $600 | Implemented |
LM0039 # 07 Y:2002 | 07 | 2002 | MODIFY STARTUP/SHUTDOWN TIMES | $10,263 | $300 | Not Implemented |
NC0236 # 01 Y:2002 | 01 | 2002 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $1,684 | $6,000 | Not Implemented |
NC0236 # 02 Y:2002 | 02 | 2002 | DEVELOP A REPAIR/REPLACE POLICY | $4,419 | $8,200 | Implemented |
NC0236 # 03 Y:2002 | 03 | 2002 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $19,606 | $550 | Not Implemented |
NC0236 # 04 Y:2002 | 04 | 2002 | USE PHOTOCELL CONTROLS | $115 | $260 | Implemented |
MI0042 # 01 Y:2002 | 01 | 2002 | UPGRADE OBSOLETE EQUIPMENT | $9,734 | $13,500 | Not Implemented |
MI0042 # 02 Y:2002 | 02 | 2002 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $6,826 | $36 | Not Implemented |
MI0042 # 03 Y:2002 | 03 | 2002 | METER WASTE WATER | $1,752 | $3,650 | Not Implemented |
MI0042 # 04 Y:2002 | 04 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,665 | $2 | Not Implemented |
MI0042 # 05 Y:2002 | 05 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,684 | $6,686 | Not Implemented |
AS0328 # 01 Y:2002 | 01 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,170 | $4,422 | Implemented |
AS0328 # 02 Y:2002 | 02 | 2002 | INSTALL OCCUPANCY SENSORS | $160 | $375 | Not Implemented |
AS0328 # 03 Y:2002 | 03 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $540 | $675 | Implemented |
AS0328 # 04 Y:2002 | 04 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,442 | $737 | Implemented |
AS0328 # 05 Y:2002 | 05 | 2002 | INSULATE BARE EQUIPMENT | $10,487 | $2,091 | Implemented |
AS0328 # 06 Y:2002 | 06 | 2002 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,223 | $9,800 | Implemented |
AS0328 # 07 Y:2002 | 07 | 2002 | TURN OFF EQUIPMENT WHEN NOT IN USE | $721 | $1,200 | Not Implemented |
AS0328 # 08 Y:2002 | 08 | 2002 | MINIMIZE WATER USAGE | $663 | $3,000 | Not Implemented |
TA0031 # 01 Y:2002 | 01 | 2002 | AIR CONDITION ONLY SPACE NECESSARY | $16,500 | $31,000 | Not Implemented |
TA0031 # 02 Y:2002 | 02 | 2002 | REPAIR AND ELIMINATE STEAM LEAKS | $11,090 | $480 | Implemented |
TA0031 # 03 Y:2002 | 03 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,000 | $840 | Implemented |
TA0031 # 04 Y:2002 | 04 | 2002 | INSTALL / REPAIR INSULATION ON STEAM LINES | $4,520 | $1,200 | Implemented |
TA0031 # 05 Y:2002 | 05 | 2002 | INSTALL OCCUPANCY SENSORS | $390 | $180 | Implemented |
TA0031 # 06 Y:2002 | 06 | 2002 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $315 | $0 | Implemented |