Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,529
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0687 # 04 Y:2000 | 04 | 2000 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,030 | $1,350 | Not Implemented |
GT0687 # 05 Y:2000 | 05 | 2000 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $5,787 | $0 | Implemented |
GT0687 # 06 Y:2000 | 06 | 2000 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $25,338 | $43,000 | Not Implemented |
GT0687 # 07 Y:2000 | 07 | 2000 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $991 | $742 | Implemented |
GT0687 # 08 Y:2000 | 08 | 2000 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $1,045 | $700 | Not Implemented |
GT0687 # 09 Y:2000 | 09 | 2000 | USE RADIANT HEATER FOR SPOT HEATING | $374 | $150 | Not Implemented |
GT0686 # 01 Y:2000 | 01 | 2000 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $74,340 | $0 | Implemented |
GT0686 # 02 Y:2000 | 02 | 2000 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,980 | $0 | Not Implemented |
GT0686 # 03 Y:2000 | 03 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,607 | $700 | Implemented |
GT0686 # 04 Y:2000 | 04 | 2000 | INSULATE BARE EQUIPMENT | $1,400 | $500 | Implemented |
GT0686 # 05 Y:2000 | 05 | 2000 | INSULATE BARE EQUIPMENT | $1,280 | $1,105 | Implemented |
GT0686 # 06 Y:2000 | 06 | 2000 | INSULATE BARE EQUIPMENT | $4,025 | $9,895 | Not Implemented |
GT0686 # 07 Y:2000 | 07 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $7,650 | $17,105 | Not Implemented |
GT0686 # 08 Y:2000 | 08 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,990 | $2,430 | Implemented |
GT0686 # 09 Y:2000 | 09 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $10,132 | $49,180 | Implemented |
GT0686 # 10 Y:2000 | 10 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $789 | $944 | Implemented |
GT0686 # 11 Y:2000 | 11 | 2000 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $540 | $0 | Not Implemented |
GT0686 # 12 Y:2000 | 12 | 2000 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $4,730 | $0 | Not Implemented |
GT0685 # 01 Y:2000 | 01 | 2000 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,280 | $0 | Implemented |
GT0685 # 02 Y:2000 | 02 | 2000 | REPROCESS SPENT OILS ON SITE FOR RE-USE | $13,650 | $11,650 | Implemented |
GT0685 # 03 Y:2000 | 03 | 2000 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $714 | $500 | Implemented |
GT0685 # 04 Y:2000 | 04 | 2000 | UPGRADE CONTROLS ON COMPRESSORS | $28,840 | $7,000 | Implemented |
GT0685 # 05 Y:2000 | 05 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $15,955 | $0 | Implemented |
GT0685 # 06 Y:2000 | 06 | 2000 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $93,536 | $30,000 | Not Implemented |
GT0685 # 07 Y:2000 | 07 | 2000 | INSTALL AUTOMATIC PACKING EQUIPMENT | $144,500 | $150,000 | Not Implemented |