Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,642
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MO0273 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,255 | $15,503 | Implemented |
MO0273 # 02 Y:2000 | 02 | 2000 | REPLACE BOILER | $35,241 | $30,000 | Implemented |
MO0273 # 03 Y:2000 | 03 | 2000 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,777 | $6,200 | Not Implemented |
MO0273 # 04 Y:2000 | 04 | 2000 | INSTALL OCCUPANCY SENSORS | $435 | $364 | Not Implemented |
MO0273 # 05 Y:2000 | 05 | 2000 | BURN WOOD BY-PRODUCTS FOR HEAT | $6,510 | $2,500 | Not Implemented |
MO0273 # 06 Y:2000 | 06 | 2000 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,960 | $0 | Not Implemented |
MO0273 # 07 Y:2000 | 07 | 2000 | INSTALL EQUIPMENT TO MOVE PRODUCT | $38,200 | $3,000 | Not Implemented |
MO0272 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,489 | $4,387 | Implemented |
MO0272 # 02 Y:2000 | 02 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $612 | $351 | Implemented |
MO0272 # 03 Y:2000 | 03 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,007 | $160 | Not Implemented |
MO0272 # 04 Y:2000 | 04 | 2000 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $30,325 | $0 | Not Implemented |
MO0272 # 05 Y:2000 | 05 | 2000 | INSTALL EQUIPMENT TO MOVE PRODUCT | $26,686 | $5,053 | Implemented |
MO0272 # 06 Y:2000 | 06 | 2000 | IMPROVE SPACE COMFORT CONDITIONING | $26,686 | $702 | Implemented |
MO0271 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,098 | $3,399 | Not Implemented |
MO0271 # 02 Y:2000 | 02 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,238 | $9,332 | Implemented |
MO0271 # 03 Y:2000 | 03 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,506 | $175 | Implemented |
MO0271 # 04 Y:2000 | 04 | 2000 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,270 | $825 | Not Implemented |
MO0271 # 05 Y:2000 | 05 | 2000 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $11,232 | $2,160 | Not Implemented |
MO0271 # 06 Y:2000 | 06 | 2000 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $2,496 | $0 | Not Implemented |
MO0271 # 07 Y:2000 | 07 | 2000 | INSTALL EQUIPMENT TO MOVE PRODUCT | $58,989 | $7,500 | Not Implemented |
MO0271 # 08 Y:2000 | 08 | 2000 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,263 | $0 | Not Implemented |
KU0535 # 01 Y:1999 | 01 | 1999 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $16,650 | $200 | Not Implemented |
KU0535 # 02 Y:1999 | 02 | 1999 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,250 | $2,640 | Implemented |
KU0535 # 03 Y:1999 | 03 | 1999 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $1,870 | $1,250 | Implemented |
KU0535 # 04 Y:1999 | 04 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $530 | $900 | Implemented |