Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,597
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0486 # 02 Y:2017 | 02 | 2017 | INSTALL OCCUPANCY SENSORS | $896 | $2,400 | n/a |
UM0486 # 03 Y:2017 | 03 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $20,120 | $18,000 | n/a |
UM0486 # 04 Y:2017 | 04 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $342 | $1,500 | n/a |
MZ0228 # 01 Y:2017 | 01 | 2017 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $20,062 | $0 | Implemented |
MZ0228 # 02 Y:2017 | 02 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,002 | $1,080 | Implemented |
MZ0228 # 03 Y:2017 | 03 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,092 | $1,772 | Implemented |
MZ0228 # 04 Y:2017 | 04 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,423 | $280 | Implemented |
MZ0228 # 05 Y:2017 | 05 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $897 | $340 | Implemented |
MZ0228 # 06 Y:2017 | 06 | 2017 | USE OPTIMUM THICKNESS INSULATION | $625 | $651 | Not Implemented |
UD0967 # 01 Y:2017 | 01 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,073 | $18,000 | Not Implemented |
UD0967 # 02 Y:2017 | 02 | 2017 | OPERATE BOILERS ON HIGH FIRE SETTING | $5,894 | $27 | Implemented |
UD0967 # 03 Y:2017 | 03 | 2017 | REPAIR OR REPLACE STEAM TRAPS | $3,938 | $7,676 | Implemented |
UD0967 # 04 Y:2017 | 04 | 2017 | INSULATE FEEDWATER TANK | $1,855 | $4,743 | Not Implemented |
UA0179 # 01 Y:2017 | 01 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $53,482 | $100,000 | Not Implemented |
UA0179 # 02 Y:2017 | 02 | 2017 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $44,167 | $500 | Not Implemented |
UA0179 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,876 | $42,452 | Not Implemented |
UA0179 # 04 Y:2017 | 04 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,851 | $250 | Implemented |
UA0179 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,243 | $1,165 | Implemented |
UA0179 # 06 Y:2017 | 06 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,934 | $6,152 | Not Implemented |
UA0179 # 07 Y:2017 | 07 | 2017 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $2,673 | $7,500 | Not Implemented |
UA0179 # 08 Y:2017 | 08 | 2017 | INSULATE BARE EQUIPMENT | $429 | $247 | Implemented |
UA0179 # 09 Y:2017 | 09 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,242 | $1,015 | Implemented |
WV0544 # 01 Y:2017 | 01 | 2017 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $455,414 | $1,455,300 | Not Implemented |
WV0544 # 02 Y:2017 | 02 | 2017 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $113,487 | $482,000 | Not Implemented |
WV0544 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $65,441 | $142,350 | Not Implemented |