Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,880
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1094 # 02 Y:2023 | 02 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,917 | $22,000 | Implemented |
OK1094 # 03 Y:2023 | 03 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $573 | $870 | Implemented |
OK1094 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,890 | $94,115 | Implemented |
OK1094 # 05 Y:2023 | 05 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $93,859 | $858,000 | Not Implemented |
OK1094 # 06 Y:2023 | 06 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $11,239 | $12,700 | Not Implemented |
NT0010 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,307 | $5,753 | Not Implemented |
NT0010 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $13,261 | $0 | Not Implemented |
NT0010 # 03 Y:2023 | 03 | 2023 | OPTIMIZE PLANT POWER FACTOR | $4,823 | $5,241 | Not Implemented |
NT0010 # 04 Y:2023 | 04 | 2023 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $37,440 | $111,000 | Not Implemented |
NT0010 # 05 Y:2023 | 05 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $1,400 | $1,600 | Not Implemented |
NT0010 # 06 Y:2023 | 06 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,423 | $0 | Not Implemented |
OK1093 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,678 | $10,052 | Implemented |
OK1093 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $420 | $900 | Implemented |
OK1093 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $29,830 | $374,400 | Implemented |
OK1093 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,723 | $1,260 | Implemented |
OK1093 # 05 Y:2023 | 05 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,087 | $343 | Implemented |
OK1093 # 06 Y:2023 | 06 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,010 | $0 | Implemented |
OK1093 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,345 | $8,534 | Implemented |
OK1093 # 08 Y:2023 | 08 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $12,354 | $1,420 | Implemented |
OK1093 # 09 Y:2023 | 09 | 2023 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $4,201 | $632 | Not Implemented |
OK1093 # 10 Y:2023 | 10 | 2023 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $31,034 | $19,400 | Not Implemented |
OK1093 # 11 Y:2023 | 11 | 2023 | CHANGE METHOD OF DEIONIZED WATER PRODUCTION | $98,980 | $367,077 | Implemented |
OK1093 # 12 Y:2023 | 12 | 2023 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $150,722 | $300,000 | Implemented |
OK1093 # 13 Y:2023 | 13 | 2023 | MAKE A NEW BY-PRODUCT | $1,221,405 | $1,600,000 | Implemented |
UD1060 # 01 Y:2023 | 01 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $139 | $0 | Implemented |