Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
25
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0301 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,899 | $1,500 | Implemented |
TT0301 # 05 Y:2023 | 05 | 2023 | SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING | $8,886 | $220 | Implemented |
TT0301 # 04 Y:2023 | 04 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $9,607 | $0 | Implemented |
TT0301 # 03 Y:2023 | 03 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $32,720 | $15,200 | Implemented |
TT0301 # 02 Y:2023 | 02 | 2023 | BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT | $40,702 | $210,000 | Not Implemented |
TT0301 # 01 Y:2023 | 01 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $47,506 | $76,760 | Not Implemented |
OK1094 # 06 Y:2023 | 06 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $11,239 | $12,700 | Not Implemented |
OK1094 # 05 Y:2023 | 05 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $93,859 | $858,000 | Not Implemented |
OK1094 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,890 | $94,115 | Implemented |
OK1094 # 03 Y:2023 | 03 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $573 | $870 | Implemented |
OK1094 # 02 Y:2023 | 02 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,917 | $22,000 | Implemented |
OK1094 # 01 Y:2023 | 01 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,672 | $2,688 | Not Implemented |
MZ0341 # 04 Y:2023 | 04 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,207 | $160 | Not Implemented |
MZ0341 # 03 Y:2023 | 03 | 2023 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $12,536 | $16,400 | Not Implemented |
MZ0341 # 02 Y:2023 | 02 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $13,839 | $3,000 | Not Implemented |
MZ0341 # 01 Y:2023 | 01 | 2023 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $18,080 | $9,000 | Not Implemented |
LT8366 # 01 Y:2023 | 01 | 2023 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $1,618 | $11,719 | n/a |
LT8366 # 03 Y:2023 | 03 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $18,863 | $61,076 | n/a |
LT8366 # 02 Y:2023 | 02 | 2023 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $2,157 | $4,313 | n/a |
TT0291 # 01 Y:2023 | 01 | 2023 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $44,264 | $3,287 | Not Implemented |
TT0291 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $41,378 | $10,100 | Implemented |
TT0291 # 03 Y:2023 | 03 | 2023 | PURCHASE APPROPRIATELY SIZED MATERIAL | $18,022 | $87,000 | Not Implemented |
TT0291 # 04 Y:2023 | 04 | 2023 | USE OPTIMUM THICKNESS INSULATION | $14,929 | $45,390 | Not Implemented |
TT0291 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,663 | $1,500 | Implemented |
TT0291 # 06 Y:2023 | 06 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $2,088 | $4,500 | Not Implemented |