Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
45
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0560 # 02 Y:2004 | 02 | 2004 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $32,756 | $23,710 | Implemented |
MA0560 # 01 Y:2004 | 01 | 2004 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $42,752 | $238,150 | Implemented |
MA0560 # 03 Y:2004 | 03 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,875 | $1,200 | Implemented |
MA0560 # 04 Y:2004 | 04 | 2004 | INSTALL OCCUPANCY SENSORS | $317 | $256 | Implemented |
MA0560 # 05 Y:2004 | 05 | 2004 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $230 | $175 | Implemented |
MA0558 # 05 Y:2004 | 05 | 2004 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $11,990 | $0 | Not Implemented |
MA0558 # 08 Y:2004 | 08 | 2004 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $979 | $240 | Not Implemented |
MA0558 # 03 Y:2004 | 03 | 2004 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $12,830 | $5,000 | Implemented |
MA0558 # 04 Y:2004 | 04 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $12,494 | $4,680 | Implemented |
MA0558 # 02 Y:2004 | 02 | 2004 | USE MINIMUM STEAM OPERATING PRESSURE | $19,575 | $1,000 | Not Implemented |
MA0558 # 06 Y:2004 | 06 | 2004 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $5,912 | $0 | Implemented |
MA0558 # 07 Y:2004 | 07 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,965 | $2,690 | Implemented |
MA0558 # 01 Y:2004 | 01 | 2004 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $28,200 | $4,500 | Implemented |
MA0551 # 01 Y:2004 | 01 | 2004 | CONVERT COMBUSTION EQUIPMENT TO BURN OIL | $36,008 | $0 | Implemented |
MA0551 # 02 Y:2004 | 02 | 2004 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $13,353 | $27,860 | Implemented |
MA0551 # 03 Y:2004 | 03 | 2004 | REDUCE VENTILATION AIR | $10,267 | $4,614 | Not Implemented |
MA0551 # 08 Y:2004 | 08 | 2004 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $1,078 | $173 | Not Implemented |
MA0551 # 04 Y:2004 | 04 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $7,302 | $4,680 | Implemented |
MA0551 # 05 Y:2004 | 05 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $2,941 | $138 | Implemented |
MA0551 # 06 Y:2004 | 06 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,601 | $850 | Implemented |
MA0551 # 10 Y:2004 | 10 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $885 | $50 | Implemented |
MA0551 # 07 Y:2004 | 07 | 2004 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,179 | $0 | Implemented |
MA0551 # 09 Y:2004 | 09 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $958 | $1,020 | Implemented |
MA0548 # 02 Y:2004 | 02 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,950 | $4,150 | Not Implemented |
MA0548 # 01 Y:2004 | 01 | 2004 | REDUCE VENTILATION AIR | $13,881 | $4,244 | Not Implemented |