IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

45

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MA0560 # 02 Y:2004 02 2004 USE DIRECT AIR SUPPLY TO EXHAUST HOODS $32,756 $23,710 Implemented
MA0560 # 01 Y:2004 01 2004 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $42,752 $238,150 Implemented
MA0560 # 03 Y:2004 03 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,875 $1,200 Implemented
MA0560 # 04 Y:2004 04 2004 INSTALL OCCUPANCY SENSORS $317 $256 Implemented
MA0560 # 05 Y:2004 05 2004 DIRECT WARMEST AIR TO COMBUSTION INTAKE $230 $175 Implemented
MA0558 # 05 Y:2004 05 2004 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $11,990 $0 Not Implemented
MA0558 # 08 Y:2004 08 2004 DIRECT WARMEST AIR TO COMBUSTION INTAKE $979 $240 Not Implemented
MA0558 # 03 Y:2004 03 2004 USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR $12,830 $5,000 Implemented
MA0558 # 04 Y:2004 04 2004 INSTALL / REPAIR INSULATION ON STEAM LINES $12,494 $4,680 Implemented
MA0558 # 02 Y:2004 02 2004 USE MINIMUM STEAM OPERATING PRESSURE $19,575 $1,000 Not Implemented
MA0558 # 06 Y:2004 06 2004 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $5,912 $0 Implemented
MA0558 # 07 Y:2004 07 2004 INSTALL / REPAIR INSULATION ON STEAM LINES $2,965 $2,690 Implemented
MA0558 # 01 Y:2004 01 2004 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $28,200 $4,500 Implemented
MA0551 # 01 Y:2004 01 2004 CONVERT COMBUSTION EQUIPMENT TO BURN OIL $36,008 $0 Implemented
MA0551 # 02 Y:2004 02 2004 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE $13,353 $27,860 Implemented
MA0551 # 03 Y:2004 03 2004 REDUCE VENTILATION AIR $10,267 $4,614 Not Implemented
MA0551 # 08 Y:2004 08 2004 DIRECT WARMEST AIR TO COMBUSTION INTAKE $1,078 $173 Not Implemented
MA0551 # 04 Y:2004 04 2004 INSTALL / REPAIR INSULATION ON STEAM LINES $7,302 $4,680 Implemented
MA0551 # 05 Y:2004 05 2004 REPAIR AND ELIMINATE STEAM LEAKS $2,941 $138 Implemented
MA0551 # 06 Y:2004 06 2004 RECOVER WASTE HEAT FROM EQUIPMENT $2,601 $850 Implemented
MA0551 # 10 Y:2004 10 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $885 $50 Implemented
MA0551 # 07 Y:2004 07 2004 PAY BILLS ON TIME TO AVOID LATE FEES $2,179 $0 Implemented
MA0551 # 09 Y:2004 09 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $958 $1,020 Implemented
MA0548 # 02 Y:2004 02 2004 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $9,950 $4,150 Not Implemented
MA0548 # 01 Y:2004 01 2004 REDUCE VENTILATION AIR $13,881 $4,244 Not Implemented