IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

502

matching recommendations
Reset
NAICS 325 Chemical Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UF0532 # 01 Y:2019 01 2019 RECOVER WASTE HEAT FROM EQUIPMENT $40,174 $25,000 Implemented
UF0532 # 02 Y:2019 02 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $23,919 $1,400 Implemented
UF0532 # 03 Y:2019 03 2019 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $9,352 $25,847 Implemented
UF0532 # 04 Y:2019 04 2019 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN $1,403 $5,998 Not Implemented
UF0532 # 05 Y:2019 05 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,301 $421 Implemented
UF0532 # 06 Y:2019 06 2019 INSULATE BARE EQUIPMENT $1,094 $230 Not Implemented
UF0532 # 07 Y:2019 07 2019 REDUCE OR ELIMINATE WASTE $19,196 $40,500 Implemented
UF0530 # 01 Y:2019 01 2019 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $94,823 $80,000 Implemented
UF0530 # 02 Y:2019 02 2019 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $60,494 $202,420 Implemented
UF0530 # 03 Y:2019 03 2019 RECOVER WASTE HEAT FROM EQUIPMENT $47,739 $25,000 Implemented
UF0530 # 04 Y:2019 04 2019 RECOVER WASTE HEAT FROM EQUIPMENT $43,693 $25,000 Implemented
UF0530 # 05 Y:2019 05 2019 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,859 $22,491 Not Implemented
UF0530 # 06 Y:2019 06 2019 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,402 $0 Implemented
UF0530 # 07 Y:2019 07 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,876 $421 Implemented
UF0530 # 08 Y:2019 08 2019 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN $1,535 $5,998 Not Implemented
UF0530 # 09 Y:2019 09 2019 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH $1,181 $2,000 Not Implemented
MI0348 # 01 Y:2019 01 2019 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $27,411 $167,280 Implemented
MI0348 # 02 Y:2019 02 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $15,401 $2,020 Implemented
MI0348 # 03 Y:2019 03 2019 UPGRADE OBSOLETE EQUIPMENT $12,811 $30,000 Implemented
MI0348 # 04 Y:2019 04 2019 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,851 $3,229 Implemented
MI0348 # 05 Y:2019 05 2019 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $6,415 $18,468 Not Implemented
MI0348 # 06 Y:2019 06 2019 USE SOLAR HEAT TO HEAT WATER $4,487 $12,390 Not Implemented
MI0348 # 07 Y:2019 07 2019 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $4,470 $10,760 Not Implemented
MI0348 # 08 Y:2019 08 2019 INSTALL OCCUPANCY SENSORS $3,201 $750 Implemented
MI0348 # 09 Y:2019 09 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,936 $7,601 Implemented