Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
166
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0656 # 06 Y:1998 | 06 | 1998 | COMBINE UTILITY METERS | $1,780 | $0 | Not Implemented |
GT0656 # 01 Y:1998 | 01 | 1998 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $9,632 | $7,000 | Implemented |
GT0656 # 04 Y:1998 | 04 | 1998 | AUTOMATE FINISHING PROCESS | $15,600 | $15,000 | Implemented |
GT0656 # 05 Y:1998 | 05 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $4,000 | $5,000 | Not Implemented |
GT0656 # 03 Y:1998 | 03 | 1998 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $1,440 | $0 | Implemented |
GT0656 # 02 Y:1998 | 02 | 1998 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $5,934 | $4,000 | Not Implemented |
GT0655 # 01 Y:1998 | 01 | 1998 | OPTIMIZE PLANT POWER FACTOR | $5,800 | $5,000 | Implemented |
GT0655 # 03 Y:1998 | 03 | 1998 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $1,582 | $3,116 | Not Implemented |
GT0655 # 07 Y:1998 | 07 | 1998 | CONVERT TO ELECTROSTATIC POWDER COATING | $4,410 | $5,400 | Not Implemented |
GT0655 # 04 Y:1998 | 04 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,677 | $4,550 | Implemented |
GT0655 # 08 Y:1998 | 08 | 1998 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $3,500 | $0 | Not Implemented |
GT0655 # 05 Y:1998 | 05 | 1998 | MINIMIZE WATER USAGE | $6,576 | $0 | Implemented |
GT0655 # 02 Y:1998 | 02 | 1998 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $10,690 | $1,250 | Implemented |
GT0655 # 06 Y:1998 | 06 | 1998 | CONVERT TO ELECTROSTATIC POWDER COATING | $7,580 | $4,800 | Not Implemented |
GT0654 # 02 Y:1998 | 02 | 1998 | INSTALL OCCUPANCY SENSORS | $150 | $52 | Not Implemented |
GT0654 # 03 Y:1998 | 03 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $170 | $108 | Not Implemented |
GT0654 # 06 Y:1998 | 06 | 1998 | PAY UTILITY BILLS ON TIME | $1,330 | $0 | Implemented |
GT0654 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,734 | $12,757 | Not Implemented |
GT0654 # 05 Y:1998 | 05 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $200 | $0 | Implemented |
GT0654 # 07 Y:1998 | 07 | 1998 | MINIMIZE WATER USAGE | $935 | $1,100 | Not Implemented |
GT0654 # 04 Y:1998 | 04 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $737 | $150 | Implemented |
GT0654 # 08 Y:1998 | 08 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $3,740 | $5,000 | Implemented |
GT0653 # 02 Y:1998 | 02 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,810 | $600 | Implemented |
GT0653 # 01 Y:1998 | 01 | 1998 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,720 | $2,000 | Not Implemented |
GT0653 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $647 | $420 | Not Implemented |