Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

42

matching recommendations
Reset
SIC 34 Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
BD0330 # 02 Y:2007 02 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,225 $8,850 Implemented
BD0330 # 01 Y:2007 01 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,133 $5,400 Implemented
BD0330 # 11 Y:2007 11 2007 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS $307,692 $5,801 Implemented
BD0330 # 10 Y:2007 10 2007 USE RADIANT HEATER FOR SPOT HEATING $81,923 $0 Not Implemented
BD0330 # 09 Y:2007 09 2007 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $621 $0 Not Implemented
BD0330 # 08 Y:2007 08 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $442 $2 Implemented
BD0330 # 07 Y:2007 07 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,489 $501 Implemented
BD0330 # 06 Y:2007 06 2007 RECOVER WASTE HEAT FROM EQUIPMENT $1,117 $0 Not Implemented
BD0330 # 05 Y:2007 05 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $160 $126 Implemented
BD0330 # 04 Y:2007 04 2007 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $2,578 $0 Not Implemented
BD0330 # 03 Y:2007 03 2007 INSTALL OCCUPANCY SENSORS $1,189 $2,100 Implemented
BD0327 # 09 Y:2007 09 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $10,900 $9,230 Not Implemented
BD0327 # 08 Y:2007 08 2007 USE PHOTOCELL CONTROLS $36,411 $10,000 Not Implemented
BD0327 # 04 Y:2007 04 2007 INSTALL REPLACEMENT DOORS $7,558 $20,000 Not Implemented
BD0327 # 01 Y:2007 01 2007 RECOVER WASTE HEAT FROM EQUIPMENT $1,018 $1,000 Not Implemented
BD0327 # 03 Y:2007 03 2007 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,520 $600 Not Implemented
BD0327 # 02 Y:2007 02 2007 USE SYNTHETIC LUBRICANT $4,257 $600 Not Implemented
BD0327 # 07 Y:2007 07 2007 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,763 $0 Not Implemented
BD0327 # 10 Y:2007 10 2007 INSTALL OCCUPANCY SENSORS $1,702 $1,200 Not Implemented
BD0327 # 11 Y:2007 11 2007 LOWER CEILING TO REDUCE CONDITIONED SPACE $816 $1,460 Not Implemented
BD0327 # 05 Y:2007 05 2007 REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY $15,124 $6,800 Not Implemented
BD0327 # 06 Y:2007 06 2007 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $24,271 $500 Not Implemented
BD0325 # 01 Y:2007 01 2007 USE RADIANT HEATER FOR SPOT HEATING $161,695 $11,200 Not Implemented
BD0325 # 02 Y:2007 02 2007 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $8,418 $15,000 Not Implemented
BD0325 # 03 Y:2007 03 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $39,183 $10,000 Not Implemented