IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

340

matching recommendations
Reset
SIC 37 Transportation Equipment
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
BD0426 # 01 Y:2013 01 2013 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION $12,183 $42,000 Not Implemented
BD0426 # 06 Y:2013 06 2013 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,416 $40 Not Implemented
BD0426 # 05 Y:2013 05 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,797 $5,872 Implemented
BD0426 # 10 Y:2013 10 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $269 $280 Not Implemented
BD0426 # 08 Y:2013 08 2013 INSTALL OCCUPANCY SENSORS $1,005 $863 Not Implemented
BD0426 # 04 Y:2013 04 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,390 $400 Implemented
BD0426 # 09 Y:2013 09 2013 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $815 $2,250 Not Implemented
BD0426 # 07 Y:2013 07 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,240 $20 Implemented
BD0426 # 02 Y:2013 02 2013 USE RADIANT HEATER FOR SPOT HEATING $6,235 $22,050 Not Implemented
BD0417 # 05 Y:2012 05 2012 USE SYNTHETIC LUBRICANT $1,301 $500 Not Implemented
BD0417 # 02 Y:2012 02 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $889 $10 Not Implemented
BD0417 # 01 Y:2012 01 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $661 $966 Implemented
BD0417 # 07 Y:2012 07 2012 USE PHOTOCELL CONTROLS $190 $50 Not Implemented
BD0417 # 06 Y:2012 06 2012 INSTALL OCCUPANCY SENSORS $1,124 $375 Implemented
BD0417 # 04 Y:2012 04 2012 RECOVER WASTE HEAT FROM EQUIPMENT $38,469 $5,000 Implemented
BD0417 # 03 Y:2012 03 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,168 $300 Not Implemented
BD0412 # 06 Y:2012 06 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,988 $2,000 Not Implemented
BD0412 # 07 Y:2012 07 2012 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $798 $40 Not Implemented
BD0412 # 01 Y:2012 01 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,670 $30,287 Not Implemented
BD0412 # 02 Y:2012 02 2012 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $4,041 $6,000 Not Implemented
BD0412 # 04 Y:2012 04 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,859 $20 Not Implemented
BD0412 # 05 Y:2012 05 2012 USE SYNTHETIC LUBRICANT $4,093 $1,200 Not Implemented
BD0412 # 03 Y:2012 03 2012 INSTALL OCCUPANCY SENSORS $4,980 $1,050 Not Implemented
BD0408 # 04 Y:2012 04 2012 RECOVER WASTE HEAT FROM EQUIPMENT $1,622 $4,000 Implemented
BD0408 # 05 Y:2012 05 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $154 $20 Implemented