Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
443
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0024 # 12 Y:2001 | 12 | 2001 | RECYCLE CASTING SAND | $765,000 | $0 | Not Implemented |
IC0024 # 11 Y:2001 | 11 | 2001 | INSTALL SET-BACK TIMERS | $2,245 | $1,741 | Implemented |
IC0024 # 10 Y:2001 | 10 | 2001 | INSTALL SET-BACK TIMERS | $4,823 | $968 | Not Implemented |
IC0024 # 04 Y:2001 | 04 | 2001 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $1,943 | $4,000 | Implemented |
IC0024 # 03 Y:2001 | 03 | 2001 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $7,403 | $2,000 | Implemented |
IC0024 # 08 Y:2001 | 08 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,811 | $7,956 | Not Implemented |
IC0024 # 09 Y:2001 | 09 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,134 | $945 | Implemented |
IC0024 # 02 Y:2001 | 02 | 2001 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $11,240 | $3,280 | Not Implemented |
IC0024 # 06 Y:2001 | 06 | 2001 | UPGRADE OBSOLETE EQUIPMENT | $9,500 | $16,800 | Not Implemented |
IC0024 # 07 Y:2001 | 07 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,642 | $32,917 | Not Implemented |
IC0024 # 01 Y:2001 | 01 | 2001 | RELOCATE OVEN / FURNACE TO MORE EFFICIENT LOCATION | $27,240 | $6,825 | Not Implemented |
IC0024 # 14 Y:2001 | 14 | 2001 | MOVE PRODUCT USING MECHANICAL MEANS | $11,000 | $7,000 | Not Implemented |
IC0024 # 05 Y:2001 | 05 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,634 | $4,300 | Implemented |
IC0024 # 13 Y:2001 | 13 | 2001 | CLEAR AND RENT EXISTING SPACE | $365,820 | $3,920 | Implemented |
IC0023 # 07 Y:2001 | 07 | 2001 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $3,070 | $2,812 | n/a |
IC0023 # 06 Y:2001 | 06 | 2001 | CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS | $11,745 | $14,000 | n/a |
IC0023 # 08 Y:2001 | 08 | 2001 | RECOVER AND REUSE WASTE MATERIAL | $14,413 | $72,000 | n/a |
IC0023 # 04 Y:2001 | 04 | 2001 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,187 | $14,750 | n/a |
IC0023 # 02 Y:2001 | 02 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $272 | $150 | n/a |
IC0023 # 05 Y:2001 | 05 | 2001 | INSTALL OCCUPANCY SENSORS | $1,046 | $501 | n/a |
IC0023 # 01 Y:2001 | 01 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,245 | $900 | n/a |
IC0023 # 03 Y:2001 | 03 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,208 | $14,105 | n/a |
IC0022 # 01 Y:2001 | 01 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,251 | $12,135 | Not Implemented |
IC0022 # 04 Y:2001 | 04 | 2001 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $1,800 | $3,280 | Not Implemented |
IC0022 # 05 Y:2001 | 05 | 2001 | INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE | $6,502 | $6,300 | Not Implemented |