Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
75
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0207 # 16 Y:1986 | 16 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $128 | $100 | Implemented |
KU0208 # 04 Y:1986 | 04 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $295 | $0 | Implemented |
KU0208 # 02 Y:1986 | 02 | 1986 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $4,084 | $100 | Implemented |
KU0207 # 15 Y:1986 | 15 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $375 | $150 | Not Implemented |
KU0207 # 14 Y:1986 | 14 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $454 | $20 | Implemented |
KU0208 # 08 Y:1986 | 08 | 1986 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $281 | $300 | Not Implemented |
KU0208 # 11 Y:1986 | 11 | 1986 | IMPROVE LUBRICATION PRACTICES | $411 | $500 | Implemented |
KU0208 # 05 Y:1986 | 05 | 1986 | INSTALL AUTOMATIC STACK DAMPER | $655 | $200 | Implemented |
KU0208 # 06 Y:1986 | 06 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $217 | $0 | Implemented |
KU0208 # 09 Y:1986 | 09 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $363 | $0 | Not Implemented |
KU0208 # 07 Y:1986 | 07 | 1986 | INSTALL AUTOMATIC STACK DAMPER | $317 | $600 | Implemented |
KU0208 # 10 Y:1986 | 10 | 1986 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $746 | $1,000 | Not Implemented |
KU0198 # 08 Y:1986 | 08 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $562 | $124 | Implemented |
KU0198 # 07 Y:1986 | 07 | 1986 | INSTALL SET-BACK TIMERS | $1,185 | $60 | Implemented |
KU0198 # 06 Y:1986 | 06 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,845 | $3,666 | Implemented |
KU0198 # 05 Y:1986 | 05 | 1986 | IMPROVE LUBRICATION PRACTICES | $2,456 | $1,724 | Implemented |
KU0198 # 04 Y:1986 | 04 | 1986 | USE MINIMUM STEAM OPERATING PRESSURE | $2,706 | $5,000 | Implemented |
KU0198 # 03 Y:1986 | 03 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,569 | $0 | Implemented |
KU0198 # 02 Y:1986 | 02 | 1986 | REPAIR AND ELIMINATE STEAM LEAKS | $17,771 | $880 | Implemented |
KU0198 # 01 Y:1986 | 01 | 1986 | INCREASE AMOUNT OF CONDENSATE RETURNED | $26,112 | $21,000 | Not Implemented |
KU0192 # 10 Y:1986 | 10 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $237 | $0 | Not Implemented |
KU0192 # 09 Y:1986 | 09 | 1986 | INSULATE BARE EQUIPMENT | $261 | $300 | Implemented |
KU0192 # 08 Y:1986 | 08 | 1986 | INSULATE BARE EQUIPMENT | $293 | $200 | Implemented |
KU0192 # 07 Y:1986 | 07 | 1986 | IMPROVE LUBRICATION PRACTICES | $2,627 | $1,700 | Not Implemented |
KU0192 # 06 Y:1986 | 06 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,390 | $100 | Not Implemented |