IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

166

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
KU0505 # 01 Y:1998 01 1998 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,140 $9,600 Implemented
KU0504 # 03 Y:1998 03 1998 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,240 $390 Not Implemented
KU0504 # 01 Y:1998 01 1998 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $14,180 $10,050 Implemented
KU0504 # 02 Y:1998 02 1998 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,210 $4,420 Implemented
KU0504 # 04 Y:1998 04 1998 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $840 $350 Implemented
KU0504 # 05 Y:1998 05 1998 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $450 $1,020 Implemented
KU0504 # 07 Y:1998 07 1998 $43,400 $82,500 Not Implemented
KU0504 # 06 Y:1998 06 1998 RECOVER AND REUSE WASTE MATERIAL $22,040 $570 Not Implemented
KU0504 # 08 Y:1998 08 1998 $8,520 $8,480 Implemented
KU0504 # 09 Y:1998 09 1998 $6,820 $18,750 Implemented
KU0502 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $7,420 $12,600 Implemented
KU0502 # 02 Y:1998 02 1998 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $840 $2,170 Not Implemented
KU0502 # 03 Y:1998 03 1998 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $280 $330 Implemented
KU0502 # 04 Y:1998 04 1998 USE SYNTHETIC LUBRICANT $210 $300 Implemented
KU0502 # 05 Y:1998 05 1998 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $2,070 $7,680 Implemented
KU0502 # 06 Y:1998 06 1998 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $1,380 $0 Implemented
KU0502 # 07 Y:1998 07 1998 $83,890 $42,990 Implemented
KU0503 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $24,460 $29,380 Implemented
KU0503 # 02 Y:1998 02 1998 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $4,580 $2,350 Implemented
KU0503 # 03 Y:1998 03 1998 INSTALL / REPAIR INSULATION ON STEAM LINES $2,650 $7,560 Implemented
KU0503 # 12 Y:1998 12 1998 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES $810 $1,050 Not Implemented
KU0503 # 10 Y:1998 10 1998 INSTALL OCCUPANCY SENSORS $790 $1,100 Implemented
KU0503 # 11 Y:1998 11 1998 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $760 $310 Implemented
KU0503 # 09 Y:1998 09 1998 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $820 $1,000 Implemented
KU0503 # 13 Y:1998 13 1998 $12,230 $41,100 Implemented