Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
146
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL2318 # 04 Y:2023 | 04 | 2023 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,046 | $0 | n/a |
UL2318 # 05 Y:2023 | 05 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,113 | $0 | n/a |
UL2318 # 02 Y:2023 | 02 | 2023 | INSTALL OCCUPANCY SENSORS | $1,925 | $6,408 | n/a |
UL2318 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $14,952 | $10,400 | n/a |
UL2318 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,544 | $12,786 | n/a |
UL2318 # 07 Y:2023 | 07 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $59,688 | $501,748 | n/a |
UL2318 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,695 | $2,160 | n/a |
UL2317 # 05 Y:2023 | 05 | 2023 | OPTIMIZE PLANT POWER FACTOR | $6,865 | $9,100 | n/a |
UL2317 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $16,039 | $148,666 | n/a |
UL2317 # 04 Y:2023 | 04 | 2023 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,720 | $500 | n/a |
UL2317 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,022 | $2,077 | n/a |
UL2317 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,159 | $0 | n/a |
UL2316 # 02 Y:2023 | 02 | 2023 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $73,247 | $137,300 | n/a |
UL2316 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $14,992 | $0 | n/a |
UL2316 # 04 Y:2023 | 04 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,026 | $0 | n/a |
UL2316 # 05 Y:2023 | 05 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $15,036 | $20,000 | n/a |
UL2316 # 06 Y:2023 | 06 | 2023 | INSTALL HYDROGEN FUEL CELL | $281,388 | $1,750,000 | n/a |
UL2316 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $112,167 | $989,084 | n/a |
UL2315 # 05 Y:2023 | 05 | 2023 | INSTALL OCCUPANCY SENSORS | $2,583 | $1,264 | Not Implemented |
UL2315 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,783 | $12,225 | Not Implemented |
UL2315 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,612 | $8,564 | Not Implemented |
UL2315 # 06 Y:2023 | 06 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,527 | $31,200 | Not Implemented |
UL2315 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $19,703 | $150,942 | Not Implemented |
UL2315 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,528 | $1,620 | Not Implemented |
UL2314 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $29,804 | $13,936 | Not Implemented |