IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

217

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NC0504 # 05 Y:2013 05 2013 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $618 $300 Implemented
NC0504 # 03 Y:2013 03 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $103 $100 Implemented
NC0504 # 04 Y:2013 04 2013 RECOVER WASTE HEAT FROM EQUIPMENT $363 $850 Not Implemented
NC0504 # 06 Y:2013 06 2013 INSTALL OCCUPANCY SENSORS $1,428 $2,892 Implemented
NC0504 # 01 Y:2013 01 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $686 $25 Not Implemented
NC0504 # 02 Y:2013 02 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $333 $50 Implemented
NC0504 # 07 Y:2013 07 2013 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $4,341 $21,429 Implemented
NC0503 # 04 Y:2013 04 2013 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $107,579 $110,000 Not Implemented
NC0503 # 07 Y:2013 07 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,203 $100 Implemented
NC0503 # 03 Y:2013 03 2013 INSTALL OCCUPANCY SENSORS $16,865 $10,990 Not Implemented
NC0503 # 05 Y:2013 05 2013 RECOVER WASTE HEAT FROM EQUIPMENT $7,771 $1,900 Not Implemented
NC0503 # 06 Y:2013 06 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $9,944 $3,969 Not Implemented
NC0503 # 01 Y:2013 01 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $128,043 $171,848 Not Implemented
NC0503 # 02 Y:2013 02 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,179 $7,472 Not Implemented
NC0502 # 07 Y:2013 07 2013 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $39 $16 Implemented
NC0502 # 01 Y:2013 01 2013 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $911 $1,200 Not Implemented
NC0502 # 04 Y:2013 04 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $485 $50 Implemented
NC0502 # 06 Y:2013 06 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $408 $25 Implemented
NC0502 # 05 Y:2013 05 2013 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $564 $525 Implemented
NC0502 # 02 Y:2013 02 2013 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $864 $600 Implemented
NC0502 # 03 Y:2013 03 2013 INSTALL OCCUPANCY SENSORS $727 $1,218 Implemented
NC0500 # 02 Y:2013 02 2013 MAKE A NEW BY-PRODUCT $86,815 $250,000 Implemented
NC0500 # 13 Y:2013 13 2013 INSTALL OCCUPANCY SENSORS $596 $1,565 Not Implemented
NC0500 # 10 Y:2013 10 2013 METER WASTE WATER $4,155 $4,200 Implemented
NC0500 # 01 Y:2013 01 2013 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS $59,689 $250,000 Not Implemented