Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0455 # 07 Y:1999 | 07 | 1999 | HIRE ADDITIONAL PERSONNEL TO REDUCE CHANGEOUT TIME | $39,560 | $1,000 | n/a |
CO0455 # 06 Y:1999 | 06 | 1999 | USE IN-PROCESS RECYCLING WHENEVER POSSIBLE | $2,180 | $3,500 | n/a |
CO0455 # 05 Y:1999 | 05 | 1999 | USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES | $39,330 | $0 | n/a |
CO0455 # 04 Y:1999 | 04 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $430 | $440 | n/a |
CO0455 # 03 Y:1999 | 03 | 1999 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,640 | $0 | n/a |
CO0455 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,020 | $220 | n/a |
CO0455 # 01 Y:1999 | 01 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $41,240 | $10,000 | n/a |
CO0454 # 05 Y:1999 | 05 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $610 | $30 | Implemented |
CO0454 # 08 Y:1999 | 08 | 1999 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $350 | $490 | Implemented |
CO0454 # 07 Y:1999 | 07 | 1999 | MINIMIZE WATER USAGE | $1,480 | $640 | Not Implemented |
CO0454 # 06 Y:1999 | 06 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $392 | $0 | Implemented |
CO0453 # 01 Y:1999 | 01 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,250 | $1,380 | Not Implemented |
CO0454 # 04 Y:1999 | 04 | 1999 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,010 | $0 | Implemented |
CO0454 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,630 | $80 | Implemented |
CO0454 # 02 Y:1999 | 02 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,460 | $7,500 | Implemented |
CO0454 # 01 Y:1999 | 01 | 1999 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $8,180 | $0 | Not Implemented |
CO0453 # 06 Y:1999 | 06 | 1999 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $320 | $890 | Not Implemented |
CO0453 # 05 Y:1999 | 05 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $670 | $320 | Not Implemented |
CO0453 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $800 | $240 | Not Implemented |
CO0453 # 03 Y:1999 | 03 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,380 | $2,150 | Not Implemented |
CO0453 # 02 Y:1999 | 02 | 1999 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $5,130 | $10,000 | Not Implemented |