Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
127
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NV0119 # 04 Y:1998 | 04 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,256 | $4,009 | Not Implemented |
NV0119 # 03 Y:1998 | 03 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,499 | $0 | Implemented |
NV0119 # 02 Y:1998 | 02 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $928 | $252 | Not Implemented |
NV0119 # 01 Y:1998 | 01 | 1998 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $60,884 | $48,211 | Implemented |
NV0118 # 07 Y:1998 | 07 | 1998 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $1,830 | $0 | Not Implemented |
NV0118 # 06 Y:1998 | 06 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $1,834 | $3,260 | Implemented |
NV0118 # 05 Y:1998 | 05 | 1998 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,870 | $0 | Implemented |
NV0118 # 04 Y:1998 | 04 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,324 | $0 | Not Implemented |
NV0118 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,687 | $56 | Not Implemented |
NV0118 # 02 Y:1998 | 02 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $331 | $180 | Implemented |
NV0118 # 01 Y:1998 | 01 | 1998 | OPTIMIZE PLANT POWER FACTOR | $2,663 | $3,333 | Implemented |
NV0117 # 03 Y:1998 | 03 | 1998 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $4,032 | $1,000 | Implemented |
NV0117 # 02 Y:1998 | 02 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $25,175 | $82,000 | Implemented |
NV0117 # 01 Y:1998 | 01 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $242 | $252 | Implemented |
NV0116 # 04 Y:1998 | 04 | 1998 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $11,871 | $50,000 | Not Implemented |
NV0116 # 01 Y:1998 | 01 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $123 | $0 | Implemented |
NV0116 # 02 Y:1998 | 02 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $808 | $200 | Implemented |
NV0116 # 03 Y:1998 | 03 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,657 | $12,973 | Not Implemented |
NV0116 # 05 Y:1998 | 05 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $175 | $0 | Not Implemented |
NV0115 # 03 Y:1998 | 03 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,937 | $10,398 | Implemented |
NV0115 # 01 Y:1998 | 01 | 1998 | OPTIMIZE PLANT POWER FACTOR | $1,772 | $2,333 | Implemented |
NV0115 # 02 Y:1998 | 02 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,392 | $1,226 | Not Implemented |
NV0115 # 04 Y:1998 | 04 | 1998 | AUTOMATE FINISHING PROCESS | $68,996 | $19,100 | Implemented |
NV0115 # 06 Y:1998 | 06 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $2,067 | $0 | Not Implemented |
NV0115 # 05 Y:1998 | 05 | 1998 | INSTALL AUTOMATIC PACKING EQUIPMENT | $358,805 | $198,720 | Not Implemented |