IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

168

matching recommendations
Reset
NAICS 3222 Converted Paper Product Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SU0239 # 03 Y:2006 03 2006 $1,365 $0 Implemented
SU0239 # 04 Y:2006 04 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,985 $440 Implemented
SU0239 # 05 Y:2006 05 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,248 $371 Implemented
SU0239 # 06 Y:2006 06 2006 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $84 $51 Implemented
SU0239 # 07 Y:2006 07 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,577 $5,660 Implemented
SU0239 # 08 Y:2006 08 2006 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $166 $270 Not Implemented
SU0239 # 09 Y:2006 09 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $223 $487 Implemented
SU0239 # 10 Y:2006 10 2006 OPTIMIZE PLANT POWER FACTOR $1,820 $6,664 Not Implemented
SU0217 # 01 Y:2005 01 2005 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $18,867 $0 Implemented
SU0217 # 02 Y:2005 02 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $16,273 $0 Not Implemented
SU0217 # 03 Y:2005 03 2005 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $9,819 $0 Implemented
SU0217 # 04 Y:2005 04 2005 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $10,785 $500 Implemented
SU0217 # 05 Y:2005 05 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,763 $954 Implemented
SU0217 # 06 Y:2005 06 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $7,934 $652 Not Implemented
SU0217 # 07 Y:2005 07 2005 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $6,167 $2,280 Implemented
SU0217 # 08 Y:2005 08 2005 OPTIMIZE PLANT POWER FACTOR $3,979 $14,487 Implemented
SU0207 # 01 Y:2005 01 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $206 $0 Implemented
SU0207 # 02 Y:2005 02 2005 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $2,133 $0 Not Implemented
SU0207 # 03 Y:2005 03 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,791 $477 Implemented
SU0207 # 04 Y:2005 04 2005 USE SYNTHETIC LUBRICANT $2,489 $2,000 Not Implemented
SU0207 # 05 Y:2005 05 2005 ADJUST VENTS TO MINIMIZE ENERGY USE $21,600 $21,422 Not Implemented
SU0207 # 06 Y:2005 06 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $55 $92 Implemented
SU0189 # 01 Y:2004 01 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,275 $0 Not Implemented
SU0189 # 02 Y:2004 02 2004 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,940 $0 Implemented
SU0189 # 03 Y:2004 03 2004 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $4,291 $378 Implemented