Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

249

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SU0244 # 11 Y:2006 11 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $448 $356 Implemented
SU0244 # 07 Y:2006 07 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,070 $1,038 Implemented
SU0244 # 05 Y:2006 05 2006 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $93,478 $10,000 Not Implemented
SU0244 # 03 Y:2006 03 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $38,250 $1,066 Not Implemented
SU0244 # 10 Y:2006 10 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $38,277 $20,000 Implemented
SU0244 # 12 Y:2006 12 2006 OPTIMIZE PLANT POWER FACTOR $11,590 $30,856 Not Implemented
SU0244 # 01 Y:2006 01 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $33,798 $0 Implemented
SU0244 # 13 Y:2006 13 2006 INSTALL EQUIPMENT TO UTILIZE WASTE FUEL $1,187,734 $4,100,000 Not Implemented
SU0244 # 09 Y:2006 09 2006 INSULATE FEEDWATER TANK $3,113 $2,058 Implemented
SU0244 # 02 Y:2006 02 2006 PAY BILLS ON TIME TO AVOID LATE FEES $8,145 $0 Implemented
SU0244 # 08 Y:2006 08 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $23,016 $5,266 Not Implemented
SU0244 # 06 Y:2006 06 2006 REPAIR AND ELIMINATE STEAM LEAKS $16,219 $432 Implemented
SU0244 # 04 Y:2006 04 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $5,614 $0 Not Implemented
SU0243 # 08 Y:2006 08 2006 INSTALL OCCUPANCY SENSORS $186 $428 Implemented
SU0243 # 02 Y:2006 02 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $8,394 $0 Implemented
SU0243 # 07 Y:2006 07 2006 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $438 $732 Not Implemented
SU0243 # 05 Y:2006 05 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $13,094 $636 Implemented
SU0243 # 01 Y:2006 01 2006 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $18,077 $0 Implemented
SU0243 # 11 Y:2006 11 2006 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $23,312 $73,075 Not Implemented
SU0243 # 04 Y:2006 04 2006 USE SYNTHETIC LUBRICANT $1,147 $0 Implemented
SU0243 # 10 Y:2006 10 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $39,436 $104,800 Not Implemented
SU0243 # 06 Y:2006 06 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,352 $1,344 Implemented
SU0243 # 03 Y:2006 03 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,730 $0 Not Implemented
SU0243 # 09 Y:2006 09 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $382 $912 Implemented
SU0245 # 15 Y:2006 15 2006 OPTIMIZE PLANT POWER FACTOR $5,643 $19,001 Not Implemented