Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
226
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0559 # 08 Y:1998 | 08 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,492 | $1,060 | Not Implemented |
UD0559 # 07 Y:1998 | 07 | 1998 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $1,752 | $2,000 | Not Implemented |
UD0559 # 03 Y:1998 | 03 | 1998 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $12,474 | $0 | Not Implemented |
UD0559 # 09 Y:1998 | 09 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,288 | $0 | Implemented |
UD0559 # 05 Y:1998 | 05 | 1998 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $3,469 | $0 | Implemented |
UD0559 # 06 Y:1998 | 06 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,782 | $500 | Implemented |
UD0559 # 04 Y:1998 | 04 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,779 | $454 | Not Implemented |
UD0559 # 02 Y:1998 | 02 | 1998 | EMPLOY MODULAR JIGS TO REDUCE PROCESS SET-UP TIME | $13,770 | $5,000 | Implemented |
UD0559 # 01 Y:1998 | 01 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $18,360 | $25,000 | Not Implemented |
UD0558 # 01 Y:1998 | 01 | 1998 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $18,790 | $8,000 | Implemented |
UD0558 # 05 Y:1998 | 05 | 1998 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $1,200 | $0 | Implemented |
UD0558 # 04 Y:1998 | 04 | 1998 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,453 | $8,000 | Implemented |
UD0558 # 03 Y:1998 | 03 | 1998 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $7,068 | $7,600 | Not Implemented |
UD0558 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,343 | $45,360 | Implemented |
UD0557 # 04 Y:1998 | 04 | 1998 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,643 | $1,440 | Not Implemented |
UD0557 # 06 Y:1998 | 06 | 1998 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,778 | $0 | Not Implemented |
UD0557 # 05 Y:1998 | 05 | 1998 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,636 | $6,680 | Not Implemented |
UD0557 # 02 Y:1998 | 02 | 1998 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $60,203 | $0 | Implemented |
UD0557 # 03 Y:1998 | 03 | 1998 | RECYCLE CLEANING SOLVENT AND REUSE | $9,078 | $0 | Not Implemented |
UD0557 # 01 Y:1998 | 01 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $42,942 | $12,000 | Implemented |
UD0556 # 01 Y:1998 | 01 | 1998 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $189,046 | $0 | Implemented |
UD0556 # 08 Y:1998 | 08 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $532 | $200 | Implemented |
UD0556 # 07 Y:1998 | 07 | 1998 | OPTIMIZE PLANT POWER FACTOR | $1,680 | $2,250 | Implemented |
UD0556 # 02 Y:1998 | 02 | 1998 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $19,800 | $0 | Implemented |
UD0556 # 03 Y:1998 | 03 | 1998 | ADJUST BURNERS FOR EFFICIENT OPERATION | $8,037 | $200 | Implemented |