IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

379

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0722 # 06 Y:2005 06 2005 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS $1,730 $0 Not Implemented
UD0722 # 07 Y:2005 07 2005 INSTALL OCCUPANCY SENSORS $104 $102 Implemented
WV0318 # 10 Y:2005 10 2005 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $1,532 $5,220 Implemented
WV0318 # 01 Y:2005 01 2005 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $39,332 $8,388 Implemented
WV0318 # 02 Y:2005 02 2005 RECOVER WASTE HEAT FROM EQUIPMENT $21,012 $3,064 Implemented
WV0318 # 03 Y:2005 03 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,845 $6,470 Implemented
WV0318 # 04 Y:2005 04 2005 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $12,757 $620 Implemented
WV0318 # 05 Y:2005 05 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,670 $587 Implemented
WV0318 # 07 Y:2005 07 2005 DEVELOP A REPAIR/REPLACE POLICY $4,198 $330 Implemented
WV0318 # 08 Y:2005 08 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,582 $11,537 Not Implemented
WV0318 # 09 Y:2005 09 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,258 $360 Implemented
WV0318 # 06 Y:2005 06 2005 COVER OPEN TANKS $5,974 $12,120 Not Implemented
WV0317 # 08 Y:2005 08 2005 INSULATE BARE EQUIPMENT $4,285 $128 Implemented
WV0317 # 01 Y:2005 01 2005 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $28,323 $0 Not Implemented
WV0317 # 02 Y:2005 02 2005 USE RADIANT HEATER FOR SPOT HEATING $23,795 $50,000 Not Implemented
WV0317 # 03 Y:2005 03 2005 UTILIZE A LESS EXPENSIVE COOLING METHOD $13,415 $5,677 Not Implemented
WV0317 # 04 Y:2005 04 2005 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $6,217 $490 Implemented
WV0317 # 05 Y:2005 05 2005 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $6,041 $60 Implemented
WV0317 # 06 Y:2005 06 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,531 $680 Implemented
WV0317 # 07 Y:2005 07 2005 DEVELOP A REPAIR/REPLACE POLICY $4,392 $855 Implemented
WV0317 # 09 Y:2005 09 2005 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $2,086 $2,295 Implemented
WV0317 # 10 Y:2005 10 2005 DEVELOP A REPAIR/REPLACE POLICY $1,435 $2,075 Not Implemented
WV0317 # 11 Y:2005 11 2005 INSTALL OCCUPANCY SENSORS $1,219 $2,680 Implemented
WV0317 # 12 Y:2005 12 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $761 $205 Implemented
WV0317 # 13 Y:2005 13 2005 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $400 $240 Implemented