Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
369
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0750 # 09 Y:2006 | 09 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $24,000 | $13,000 | Implemented |
UD0750 # 08 Y:2006 | 08 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $39,020 | $135,999 | Not Implemented |
UD0750 # 07 Y:2006 | 07 | 2006 | USE OPTIMUM THICKNESS INSULATION | $41,225 | $39,892 | Not Implemented |
UD0750 # 06 Y:2006 | 06 | 2006 | INCREASE AMOUNT OF CONDENSATE RETURNED | $44,000 | $25,000 | Implemented |
UD0750 # 05 Y:2006 | 05 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $56,000 | $0 | Not Implemented |
UD0750 # 04 Y:2006 | 04 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $79,000 | $45,000 | Implemented |
UD0750 # 03 Y:2006 | 03 | 2006 | REPAIR OR REPLACE STEAM TRAPS | $155,000 | $187,200 | Implemented |
UD0750 # 02 Y:2006 | 02 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $226,890 | $120,000 | Implemented |
UD0750 # 01 Y:2006 | 01 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $273,386 | $100,000 | Not Implemented |
UD0749 # 01 Y:2006 | 01 | 2006 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $973,467 | $1,500,000 | Not Implemented |
UD0749 # 02 Y:2006 | 02 | 2006 | REDUCE VENTILATION AIR | $359,088 | $0 | Not Implemented |
UD0749 # 03 Y:2006 | 03 | 2006 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $211,000 | $7,200 | Implemented |
UD0749 # 13 Y:2006 | 13 | 2006 | USE MINIMUM SAFE OVEN VENTILATION | $4,400 | $0 | Implemented |
UD0749 # 12 Y:2006 | 12 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,896 | $13,819 | Not Implemented |
UD0749 # 11 Y:2006 | 11 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,254 | $0 | Implemented |
UD0749 # 10 Y:2006 | 10 | 2006 | INSTALL TIMERS AND/OR THERMOSTATS | $22,598 | $20,000 | Implemented |
UD0749 # 09 Y:2006 | 09 | 2006 | UPGRADE CONTROLS ON COMPRESSORS | $25,009 | $45,000 | Implemented |
UD0749 # 08 Y:2006 | 08 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $98,501 | $34,560 | Implemented |
UD0749 # 07 Y:2006 | 07 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $111,197 | $15,000 | Not Implemented |
UD0749 # 06 Y:2006 | 06 | 2006 | MINIMIZE NON-ESSENTIAL MATERIAL IN HEAT TREATMENT PROCESS | $127,000 | $20,000 | Not Implemented |
UD0749 # 05 Y:2006 | 05 | 2006 | INSULATE BARE EQUIPMENT | $128,436 | $44,181 | Implemented |
UD0749 # 04 Y:2006 | 04 | 2006 | HEAT TREAT PARTS ONLY TO REQUIRED SPECIFICATIONS OR STANDARDS | $151,097 | $0 | Not Implemented |
UM0308 # 07 Y:2006 | 07 | 2006 | INSULATE BARE EQUIPMENT | $142 | $310 | Not Implemented |
UM0308 # 06 Y:2006 | 06 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $392 | $1,000 | Implemented |
UM0308 # 05 Y:2006 | 05 | 2006 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $536 | $300 | Implemented |