IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

194

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD1020 # 08 Y:2020 08 2020 TURN OFF EQUIPMENT WHEN NOT IN USE $832 $0 Not Implemented
UD1019 # 01 Y:2020 01 2020 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $2,684 $0 Implemented
UD1019 # 02 Y:2020 02 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,924 $1,000 Not Implemented
UD1019 # 03 Y:2020 03 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,086 $0 Not Implemented
UD1019 # 04 Y:2020 04 2020 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $9,326 $1,400 Not Implemented
UD1019 # 05 Y:2020 05 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $28,713 $11,014 Not Implemented
UD1019 # 06 Y:2020 06 2020 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $21,134 $7,500 Not Implemented
UD1019 # 07 Y:2020 07 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,619 $82,620 Implemented
UD1019 # 08 Y:2020 08 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,469 $10,920 Not Implemented
WV0596 # 01 Y:2020 01 2020 ELIMINATE SHUTDOWNS OF CONTROLS DUE TO OVERHEATING $103,798 $40,718 Implemented
WV0596 # 02 Y:2020 02 2020 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $8,186 $20,034 Implemented
WV0596 # 03 Y:2020 03 2020 INSTALL OCCUPANCY SENSORS $7,560 $7,967 Implemented
WV0596 # 04 Y:2020 04 2020 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $6,964 $30 Not Implemented
WV0596 # 05 Y:2020 05 2020 UPGRADE CONTROLS ON COMPRESSORS $6,754 $7,949 Implemented
WV0596 # 06 Y:2020 06 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,079 $10,000 Implemented
WV0596 # 07 Y:2020 07 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,729 $1,600 Implemented
WV0596 # 08 Y:2020 08 2020 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $3,333 $14,200 Not Implemented
WV0596 # 09 Y:2020 09 2020 INSULATE BARE EQUIPMENT $2,311 $1,566 Implemented
WV0596 # 10 Y:2020 10 2020 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,829 $0 Not Implemented
WV0596 # 11 Y:2020 11 2020 DEVELOP A REPAIR/REPLACE POLICY $1,750 $372 Implemented
WV0596 # 12 Y:2020 12 2020 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,108 $1,828 Implemented
WV0596 # 13 Y:2020 13 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $746 $60 Implemented
WV0596 # 14 Y:2020 14 2020 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $626 $4,034 Implemented
WV0596 # 15 Y:2020 15 2020 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM $507 $700 Implemented
WV0596 # 16 Y:2020 16 2020 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $326 $1,500 Implemented