IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

118

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0632 # 06 Y:2001 06 2001 $11,700 $2,112 Implemented
OK0626 # 03 Y:2001 03 2001 INSTALL OCCUPANCY SENSORS $534 $1,045 n/a
OK0626 # 01 Y:2001 01 2001 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $4,472 $11,200 n/a
OK0626 # 05 Y:2001 05 2001 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $28,667 $14,150 n/a
OK0626 # 04 Y:2001 04 2001 RECOVER WASTE HEAT FROM EQUIPMENT $25,294 $2,457 n/a
OK0626 # 02 Y:2001 02 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,077 $15,842 n/a
OK0626 # 06 Y:2001 06 2001 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $3,044 $2,350 n/a
OK0621 # 03 Y:2001 03 2001 RECOVER WASTE HEAT FROM EQUIPMENT $2,550 $1,185 Implemented
OK0621 # 05 Y:2001 05 2001 $47,308 $16,792 Not Implemented
OK0621 # 04 Y:2001 04 2001 $50,500 $25,810 Implemented
OK0621 # 02 Y:2001 02 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,000 $300 Implemented
OK0621 # 01 Y:2001 01 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,536 $13,800 Implemented
OK0619 # 02 Y:2001 02 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,585 $18,400 Not Implemented
OK0619 # 01 Y:2001 01 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $792 $310 Implemented
OK0619 # 08 Y:2001 08 2001 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE $2,200 $1,326 Implemented
OK0619 # 09 Y:2001 09 2001 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,082 $3,936 Not Implemented
OK0619 # 03 Y:2001 03 2001 INSTALL OCCUPANCY SENSORS $816 $878 Not Implemented
OK0619 # 04 Y:2001 04 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,184 $200 Implemented
OK0619 # 05 Y:2001 05 2001 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $1,191 $1,423 Not Implemented
OK0619 # 06 Y:2001 06 2001 USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS $38,340 $12,500 Not Implemented
OK0619 # 07 Y:2001 07 2001 CHANGE ZONE REHEAT COILS TO VARIABLE AIR VOLUME BOXES $68,500 $15,000 Implemented
OK0619 # 13 Y:2001 13 2001 $877 $0 Implemented
OK0619 # 10 Y:2001 10 2001 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $12,577 $3,000 Implemented
OK0619 # 11 Y:2001 11 2001 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $11,523 $10,275 Implemented
OK0619 # 12 Y:2001 12 2001 $29,565 $10,000 Not Implemented