IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

133

matching recommendations
Reset
NAICS 335 Electrical Equipment, Appliance, and Component Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WV0369 # 18 Y:2008 18 2008 UTILIZE A LESS EXPENSIVE COOLING METHOD $819 $1,484 Not Implemented
WV0369 # 19 Y:2008 19 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $563 $585 Implemented
WV0369 # 20 Y:2008 20 2008 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $389 $470 Implemented
WV0345 # 01 Y:2006 01 2006 ADJUST BURNERS FOR EFFICIENT OPERATION $390,000 $140,000 n/a
WV0345 # 02 Y:2006 02 2006 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $38,402 $8,000 Not Implemented
WV0345 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $35,574 $60,657 Implemented
WV0345 # 04 Y:2006 04 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $22,653 $26,300 Not Implemented
WV0345 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $15,346 $2,805 Implemented
WV0345 # 06 Y:2006 06 2006 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM $14,670 $1,000 Implemented
WV0345 # 07 Y:2006 07 2006 REDUCE VENTILATION AIR $10,829 $6,280 Not Implemented
WV0345 # 08 Y:2006 08 2006 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $9,402 $1,000 Implemented
WV0345 # 09 Y:2006 09 2006 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $6,834 $10,400 Not Implemented
WV0345 # 10 Y:2006 10 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,809 $49,405 Implemented
WV0345 # 11 Y:2006 11 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $5,570 $0 Not Implemented
WV0345 # 12 Y:2006 12 2006 DEVELOP A REPAIR/REPLACE POLICY $5,468 $800 Implemented
WV0345 # 13 Y:2006 13 2006 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $3,389 $6,500 Not Implemented
LE0232 # 01 Y:2006 01 2006 $35,100 $3,200 Not Implemented
LE0232 # 02 Y:2006 02 2006 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $33,102 $38,465 Not Implemented
LE0232 # 03 Y:2006 03 2006 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $7,750 $3,510 Not Implemented
LE0232 # 04 Y:2006 04 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,787 $500 Not Implemented
LE0232 # 05 Y:2006 05 2006 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $3,612 $620 Not Implemented
LE0232 # 06 Y:2006 06 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $809 $60 Not Implemented
LE0232 # 07 Y:2006 07 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $363 $500 Not Implemented
LE0232 # 08 Y:2006 08 2006 INSTALL OCCUPANCY SENSORS $7,549 $2,440 Not Implemented
LE0232 # 09 Y:2006 09 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $20,445 $51,983 Not Implemented