IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

181

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WV0345 # 11 Y:2006 11 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $5,570 $0 Not Implemented
WV0345 # 12 Y:2006 12 2006 DEVELOP A REPAIR/REPLACE POLICY $5,468 $800 Implemented
WV0345 # 13 Y:2006 13 2006 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $3,389 $6,500 Not Implemented
LE0237 # 01 Y:2006 01 2006 REDESIGN PROCESS $149,763 $12,500 Not Implemented
LE0237 # 02 Y:2006 02 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $89,692 $7,500 Not Implemented
LE0237 # 03 Y:2006 03 2006 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $64,774 $2,000 Implemented
LE0237 # 04 Y:2006 04 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,057 $1,000 Implemented
LE0237 # 05 Y:2006 05 2006 ADJUST BURNERS FOR EFFICIENT OPERATION $3,961 $200 Not Implemented
LE0237 # 06 Y:2006 06 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,658 $3,000 Not Implemented
LE0237 # 07 Y:2006 07 2006 INSTALL OCCUPANCY SENSORS $3,162 $900 Implemented
LE0236 # 01 Y:2006 01 2006 REDESIGN PROCESS $328,340 $1,000,000 Not Implemented
LE0236 # 02 Y:2006 02 2006 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $123,125 $25,000 Not Implemented
LE0236 # 03 Y:2006 03 2006 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $23,441 $17,600 Not Implemented
LE0236 # 04 Y:2006 04 2006 OPTIMIZE PLANT POWER FACTOR $22,758 $42,650 Not Implemented
LE0236 # 05 Y:2006 05 2006 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $15,083 $2,500 Implemented
LE0236 # 06 Y:2006 06 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $8,063 $2,750 Not Implemented
LE0236 # 07 Y:2006 07 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $5,742 $300 Not Implemented
LE0236 # 08 Y:2006 08 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,686 $300 Not Implemented
LE0236 # 09 Y:2006 09 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,309 $700 Not Implemented
LE0235 # 01 Y:2006 01 2006 $1,380,000 $3,000,000 Not Implemented
LE0235 # 02 Y:2006 02 2006 PREHEAT COMBUSTION AIR WITH WASTE HEAT $202,503 $95,000 Implemented
LE0235 # 03 Y:2006 03 2006 UPGRADE OBSOLETE EQUIPMENT $192,971 $250,000 Implemented
LE0235 # 04 Y:2006 04 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $73,559 $36,000 Not Implemented
LE0235 # 05 Y:2006 05 2006 ADJUST BURNERS FOR EFFICIENT OPERATION $66,844 $100 Implemented
LE0235 # 06 Y:2006 06 2006 ADJUST BURNERS FOR EFFICIENT OPERATION $63,349 $20,000 Implemented